4.2 Comments<br />

The Committee found the cost estimate to be well-advanced for this stage of the project.<br />

The TPC range of $197-256 million (AY) is reasonable.<br />

The NOνA location and acquisition plan are not yet finalized—this provides the highest<br />

level of uncertainty for the project. The Integrated Project Team should work aggressively to<br />

finalize these decisions immediately. These key decisions will help to clarify uncertainties on<br />

the cost estimate and schedule (critical path) and should be given the highest priority. Allocation<br />

of contingency to the CF WBS should be evaluated with the same rigor as the other elements.<br />

Overall, the NOνA project is made up of a small number of systems and procurements.<br />

Areas of cost risk that require attention are:<br />

• Scintillator and PVC—Tied to volatile oil prices.<br />

• WLSF—Single vendor recently increased price to approximately 60 percent from<br />

earlier estimates. A quote is now available, but there remains currency and single<br />

vendor risks. Work is progress to solicit alternative vendors.<br />

• Site Improvements/Building—Design/Build strategy is proposed to ensure that the<br />

science requirements are clearly identified and confirmed with collaboration.<br />

• Integration—Emphasize early prototyping of the Near and Far Detectors to ensure<br />

defects (or value engineering) are identified early on.<br />

• Quality Control/<strong>Database</strong> Management—Many parts repeated up to 20,000 times.<br />

Additional staff, testing, and documentation may be required.<br />

• Spares to account for infant mortality (electronics) and breakage/defects to achieve<br />

CD-4.<br />

The project is using an effective methodology for contingency. Assessment is reasonable<br />

in most areas and should be repeated prior to CD-2, incorporating decisions on the site location,<br />

building, and acquisition strategy. The 100 percent contingency assessment on integration labor<br />

should be reviewed for accuracy.<br />

The detailed Basis of Estimate (BOE) was not fully documented. Although, it is not<br />

necessary for CD-1, a comprehensive BOE (with quotations and detailed estimates) is required<br />

for CD-2.<br />

Project <strong>Off</strong>ice staff currently have off-project responsibilities that may create a<br />

bottleneck in configuration control and management processes. Prior to CD-2, staffing should be<br />

reviewed to ensure key configuration and QA staffing needs are adequate.<br />