integration and assembly tasks should be well understood prior to CD-2.<br />

A rough “technically-limited” funding profile was derived by the project team from the AY<br />

cost and schedule loaded profile. Cumulative planned R&D and PED work in FY 2007 will<br />

inundate available funding (assuming this work is fully committed) and will leave no available<br />

funding contingency for solving problems or maintaining schedule. The adequacy of R&D/PED<br />

funding is also dependent on resolution of the acquisition strategy. The FY 2008 funding assumes<br />

construction funds that require CD-2 approval. Once a funding profile is established, the project<br />

team should review its resource-loaded schedule to ensure success on NOνA’s commitment to<br />

DOE.<br />

Table 5-1.<br />

NOvA DOE Proposed Funding Estimate (Escalated M$)<br />

AY$ Assumes a Profile From the NOvA Cost & Schedule in Open Plan<br />

5.3 Recommendations<br />

1. Develop FTE resource estimates for the NOνA project (including zero cost<br />

physicists) immediately and communicate the project’s needs throughout laboratory<br />

management and the NOνA collaboration.<br />

2. Recommend approval of CD-1.<br />

26