3. CONVENTIONAL FACILITIES<br />

3.1 Findings<br />

The project team developed a conceptual design for the site and building at the proposed<br />

Ash River site. The site was selected as the best of five proposed sites. Preliminary borings<br />

were completed at the site and additional geotechnical borings are planned.<br />

A bottoms-up estimate was prepared by the project team. The contingency was assigned<br />

using guidance from the DOE cost estimating guide. The schedule was developed by the project<br />

team but does not reflect the recent decision to use a design build contract strategy.<br />

An Architect/Engineer (AE) will be used to evaluate the schedule and prepare an<br />

independent cost estimate.<br />

Value Engineering studies were conducted for the roof structure and the aisle access.<br />

The AE will perform additional studies of the secondary containment and the cut and fill<br />

optimization.<br />

An AE will be used to prepare the 30 percent design package. The schedule shows the<br />

30 percent design starting in October 2006, with an expected completion in January 2007.<br />

DOE plans to award a cooperative agreement with a third-party to award and<br />

cooperatively manage the design build contract for the facility.<br />

The risk assessment was documented in the CDR.<br />

3.2 Comments<br />

Evaluation and selection of the preferred site (Ash River) and alternative site (Orr-Buyk)<br />

was based on a sound decision and information gathering process.<br />

The use of an AE to do an independent review of the conceptual design estimate and<br />

schedule is commendable. The schedule should be revised to reflect the proposed design build<br />

contracting method.<br />

19