The Committee concluded that currently the NOνA cost estimate is within the range of<br />
costs provided in the draft Project Execution Plan and the range could be used as a basis for<br />
requesting CD-1, if supported by an appropriate funding profile.<br />
4.3 Recommendations<br />
1. Reassess contingency on the entire project after finalizing the conventional building<br />
acquisition strategy and siting.<br />
2. Use a TPC range of $197-256 million for requesting CD-1 approval.<br />
24