Project timetable with provisional dates<br />
Process<br />
Establishing<br />
Steering Group<br />
Task Initiation date Completion<br />
date<br />
Establishing Working<br />
Group<br />
Agreeing<br />
Governance<br />
arrangements<br />
Resource allocation<br />
(Staffing and<br />
administrative<br />
support)<br />
<strong>JSNA</strong> elements<br />
Developing preliminary<br />
outcomes framework<br />
Demographic and<br />
health profile -<br />
Overview<br />
Inequalities in terms of<br />
wider determinants<br />
(housing, environment,<br />
economics, etc)<br />
Review of needs<br />
assessments complete<br />
and review scope of<br />
those underway<br />
Consultation with<br />
public and patients<br />
(Stakeholder<br />
consultation)<br />
Oct 2007 Oct 2007 Oct 2007<br />
Nov 2007 Nov 2007 Nov 2007<br />
Jan 2008 Mar 2008 Apr 2008<br />
Nov 2007 In progress May 2008<br />
Jan 2008 Jun 2008 Jun 2008<br />
Jan 2007 In progress Sep 2008<br />
Jan 2007 In progress Sep 2008<br />
Apr 2008 In progress Sep 2008<br />
Apr 2008<br />
In progress Dec 2008<br />
Map of local services To be started n/a Sep - Dec 2008<br />
Review of evidence of<br />
effectiveness of<br />
interventions<br />
1.1.1. Output<br />
Prioritisation in terms<br />
of health and wellbeing<br />
needs of the<br />
population<br />
To be<br />
started; Pan<br />
London<br />
approach<br />
also being<br />
considered<br />
n/a<br />
Target date Jun 2008<br />
status<br />
Sep 2008 – Mar<br />
2009<br />
To be started n/a Jan-Mar 2009<br />
Strategic To be started Mar-Jun 2009<br />