These stages are applicable to all projects. However, the durations of those stages will vary based<br />

on the specific scope of work required. More complex projects involving extensive permitting and<br />

land acquisition tend to be the longest duration projects, while projects that have limited<br />

permitting needs and fully utilize existing ROW typically can be placed in service in the shortest<br />

time. With all projects, opportunities exist to shorten the development lifecycle. The NY Transco<br />

is prepared to accelerate those projects the State determines to be most significant and needed.<br />

Most of the Projects are moderately scaled and can be constructed in less time than illustrated.<br />

The 2nd Rock Tavern - Ramapo 345kV Line and the Marcy South Series Compensation and Fraser<br />

– Coopers Corners Reconductoring projects have been initiated and therefore could be expected<br />

to be in-service in a shorter duration.<br />

The Immediately Actionable Projects have been on-going and will continue to progress until a<br />

commitment of significant funding is required. An approved cost recovery mechanism will be<br />

necessary to advance these projects to completion as well as for the remaining Projects before<br />

moving them beyond conceptual engineering.<br />

The table on the following page lists the projects, their status, and a projected in-service date.<br />

17