Meyer-Eelpot Road-Ecogen-Flat Street-Greenidge 115 kV Line Reconductoring<br />
Project to Enable Wind Generation<br />
Project Description:<br />
Reconductor the existing 115 kV line from Meyer Substation to Eelpot Road Substation to Ecogen<br />
Substation to Flat Street Substation to Greenidge Substation with a conductor sized to no less than 1033<br />
ACSR or equivalent (1250 A summer normal). The existing line extends from the Village of Dansville<br />
(Livingston County) to the Village of Dresden (Yates County). All terminals of the project are located in<br />
NYISO Zone C.<br />
Project Size:<br />
Length: 43.5 miles<br />
Voltage: 115kV<br />
Anticipated rating (summer normal): 1250 A<br />
Terminal Stations and required upgrades:<br />
The terminal substations are Meyer, Eelpot Road, Ecogen, Flat Street, and Greenidge. The 115 kV<br />
buswork, switches, and CT’s at Greenidge and Meyer, the CT’s at Flat Street, and the 115 kV switches at<br />
Eelpot Road Substations will need to be upgraded to match the capacity of the 1033 ACSR conductor.<br />