Meyer-Eelpot Road-Ecogen-Flat Street-Greenidge 115 kV Line Reconductoring<br />

Project to Enable Wind Generation<br />

Project Description:<br />

Reconductor the existing 115 kV line from Meyer Substation to Eelpot Road Substation to Ecogen<br />

Substation to Flat Street Substation to Greenidge Substation with a conductor sized to no less than 1033<br />

ACSR or equivalent (1250 A summer normal). The existing line extends from the Village of Dansville<br />

(Livingston County) to the Village of Dresden (Yates County). All terminals of the project are located in<br />

NYISO Zone C.<br />

Project Size:<br />

Length: 43.5 miles<br />

Voltage: 115kV<br />

Anticipated rating (summer normal): 1250 A<br />

Terminal Stations and required upgrades:<br />

The terminal substations are Meyer, Eelpot Road, Ecogen, Flat Street, and Greenidge. The 115 kV<br />

buswork, switches, and CT’s at Greenidge and Meyer, the CT’s at Flat Street, and the 115 kV switches at<br />

Eelpot Road Substations will need to be upgraded to match the capacity of the 1033 ACSR conductor.<br />