New York Transmission Company - Energy Highway
New York Transmission Company - Energy Highway
New York Transmission Company - Energy Highway
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
These projects and the Immediately Actionable Projects are necessary to maintain reliability in the<br />
event of the retirement of Indian Point or other downstate generation.<br />
Projects to Enable Wind Generation<br />
These actionable Projects to Enable Wind Generation are identified in the NYISO’s 2010 Wind Study.<br />
They are primarily beneficial in enabling the full energy output from wind facilities in Jefferson County<br />
and in the Western <strong>New</strong> <strong>York</strong> regions to be delivered throughout <strong>New</strong> <strong>York</strong> State. The wind<br />
development projects currently in the NYISO queue have been re-evaluated and support the<br />
completion of these projects. As currently proposed, the start time of these projects would be<br />
advanced so that the completion of these projects would be aligned with the timing of the<br />
construction of the wind projects. The estimated total investment for these projects is $ 435 million.<br />
The projects included in this category are:<br />
1. Canandaigua – Hillside and Hillside – Watercure Road 230 kV Lines Reconfiguration<br />
2. Montour Falls – Hillside 115 kV Line Reconductoring<br />
3. Hillside – North Waverly 115 kV Line Reconductoring<br />
4. Canandaigua – Avoca – Hillside 230 kV Line Reconductoring<br />
5. Delhi – Colliers 115 kV Line Reconductoring<br />
6. Bennett – Howard – Bath – Montour Falls 115 kV Line Reconductoring<br />
7. Bennett – Moraine Road – Meyer 115 kV Line Reconductoring<br />
8. Meyer – Eel Pot Rd – Ecogen – Flat St. – Greenidge 115 kV Line Reconductoring<br />
9. Coffeen St. – Adirondack <strong>New</strong> 345 kV Line<br />
5