<strong>Transmission</strong> to Un-bottle Staten Island Generation<br />
Project to Address Potential Indian Point/Downstate Generation Retirement<br />
Project Description:<br />
Un-bottling Staten Island generation resources will occur in two phases. Phase 1 would mitigate a<br />
contingency within <strong>New</strong> <strong>York</strong> City by separating a common pipe double leg feeder into two separate<br />
feeders with independent positions at the Goethals and Linden Substations. Phase 2 increases<br />
transmission capacity by adding forced cooling to existing feeders between Goethals, Gowanus, and<br />
Farragut. The Project would be located in Staten Island and Brooklyn, <strong>New</strong> <strong>York</strong> and Union County<br />
(Linden), <strong>New</strong> Jersey. This project is located entirely in NYISO Zone J.<br />
Project Size:<br />
Phase 1: The length of the feeder, operating voltage level (345 kV) and ratings would not change.<br />
However the cables will be able to carry an additional of 280MW.<br />
Phase 2: The length of the feeders, operating voltage level (345 kV) would not change but the ratings<br />
would increase by 200 MW.<br />
Total Project Size: 480 MW<br />
Terminal Stations and required upgrades:<br />
The terminal stations are:<br />
1) Goethals 345 kV substation where a bus position needs to be established for the feeder separation.<br />
2) Linden 345 kV substation where a bus position needs to be established for the feeder separation.<br />