Section G: Fee<br />
Provided below are the <strong>Kessler</strong> <strong>Consulting</strong> staff members that will be available to the City. As<br />
you can see, the City will receive our most highly experienced staff at very competitive rates.<br />
<strong>Kessler</strong> <strong>Consulting</strong> typically works on a time-and-materials basis to deliver the greatest value to<br />
our clients. Based on our very competitive hourly rates and our staff’s high level of expertise,<br />
we believe KCI provides the greatest value for our client’s investment, because in any<br />
consulting engagement, time is the commodity. Competitive rates maximize the time available!<br />
Our rates include all overhead and direct and indirect costs. All expenses (travel, copies,<br />
postage, etc.) are billed at cost without markup.<br />
POSITION EMPLOYEE RATE<br />
Project Director/Principal Mitch <strong>Kessler</strong> $180/hour<br />
Project Manager Don Ross $135/hour<br />
Senior Consultants Robin Mitchell, Miriam Zimms $135/hour<br />
Consultant Lisa Lamppert $85/hour<br />
Research Analysts John Burkett, Maureen Schaefer $70/hour<br />
Admin/Technical Support Lisa LeVine $50/hour<br />
As outlined in the Proposed Scope of Services detail, Section F of this submittal, KCI offers the<br />
following phased and tasked approach to the solid waste and recycling services assessment<br />
requested. KCI believes it is essential to first review the system and analyze the options<br />
available in Phase I, and then based on these results, design a plan and implementation<br />
strategy in Phase II that best meets the goals and objectives of the City. Provided for each major<br />
task is the expected total work hours for our staff and the cost of service.<br />
Task 1<br />
Task 2<br />
‣ KCI will initiate the project by conducting a systematic “top-to-bottom” review of the<br />
City’s current solid waste system. We expect this task to take approximately 120 days.<br />
Estimated Cost for Task 1 Activities: $20,115<br />
Estimated total staff hours: 208<br />
‣ KCI will assist the City in the development of a Solid Waste Operational Plan to establish<br />
system goals for the next five years. We expect this task to take approximately 90 days.<br />
Estimated Cost for Task 2 Activities: $23,075<br />
Estimated total staff hours: 236<br />
KCI Proposals 2012\North Miami Beach\G Fee G-1