04.11.2014 Views

Full Issue (17 MB) - Pile Driving Contractors Association

Full Issue (17 MB) - Pile Driving Contractors Association

Full Issue (17 MB) - Pile Driving Contractors Association

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

The Harvey Canal Project:<br />

Saving Time, Saving<br />

Money and Saving Lives<br />

For years, more than 200,000 homes and businesses in<br />

Louisiana’s Jefferson Parish have been at risk. Their<br />

only flood protection from a major canal on the Gulf<br />

Intracoastal Water Way has been a short earthen levee or<br />

bulkheads the property owners built themselves.<br />

“It’s caused us nightmares,” says Giuseppe Miserendino,<br />

executive director of the West Jefferson Levee District.<br />

“After this hurricane season, we won’t have to worry about<br />

it.”<br />

That’s because crews are finishing a $250 million steel<br />

and concrete floodwall along the Harvey Canal that’ll rise<br />

19 feet above land – more than twice as tall as the earthen<br />

levee and far more solid. The floodwall will stretch more<br />

than 3 miles, and besides potentially saving lives, it’s also<br />

been an award-winning lesson in saving time and money.<br />

Building a T-wall<br />

Designs for the Harvey Canal project called for a T-wall<br />

(built like an inverted T). A total of about 30,000 yards of<br />

concrete will be set atop 7,800 steel H-piles, some of which<br />

are as long as 140 feet. To install piles that long, contractors<br />

would normally get the pile delivered in two pieces, install<br />

the bottom half, then splice on the top. For this project,<br />

though, that would have been too expensive and taken too<br />

much time.<br />

The crews at Cajun Deep Foundations, a subsidiary of<br />

specialty contractor Cajun Industries, developed a second<br />

option. They asked Nucor-Yamato Steel to roll the piles<br />

at full length. All told, more than 1 million linear feet of<br />

HP14 x 89 piles will be used. About 900 piles still needed to<br />

be spliced, but with a project that required a total of 7,800<br />

piles, Cajun’s idea saved nearly $8 million in splicing costs<br />

alone, says Chris Thompson, a Cajun project manager. And<br />

that doesn’t include the savings from getting the work done<br />

so much quicker.<br />

“That amount,” Thompson says, “far exceeds the $8<br />

million saved from splicing.”<br />

The solution helped the Army Corps of Engineers sus-<br />

• Q4 • 2009<br />

71

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!