<strong>Hillsborough</strong> <strong>Community</strong> <strong>College</strong>: <strong>Brandon</strong> Campus<br />
- Sabrina Peacock, Business Technologies<br />
- Ellen Cangi, Associate of Arts<br />
- Richard Zaborosky, Facilities<br />
- Joe Bentrovato, Student Services<br />
- Maria Muniz, Campus President’s Office<br />
- Edwin Kelley, Campus Services<br />
The conversation focused on the changes observed since the adoption of the 2005 Master Plan for<br />
the campus. The primary focus areas discussed by the Master Planning Committee included<br />
Student Enrollment and Space Utilization, New Facilities and Reorganization, and Academic<br />
Programs.<br />
3.9.2.1 Student Enrollment and Space Utilization<br />
Growth in the campus headcount has required optimizing utilization of current space on campus.<br />
Utilization of the existing facilities is very high, and enrollments for the upcoming semester are<br />
higher than expected. The campus is considering hiring more adjunct faculty and staggering class<br />
times in order to accompany more students while minimizing traffic congestion. The campus does<br />
experience a lull in the mid afternoons, while the campus is at full capacity in the morning and the<br />
evening.<br />
3.9.2.2 New Facilities / Reorganization<br />
Since 2005, the Student Services Building has been completed, and has made a big impact on the<br />
ability to deliver services. The building is functioning well, and the campus is happy with the space.<br />
Other changes to be addressed during this Master Plan preparation include:<br />
- Head Start program has been removed from campus, and the property it occupied needs to<br />
be considered for reprogramming.<br />
- The HCC <strong>Brandon</strong> Campus has also ended its lease of the Pinebrooke Business Park<br />
Facilities<br />
- Continuing Education Programs are to be moved to the Ybor Campus<br />
- Building A6 from 2005 Master Plan is too large for funding mechanisms anticipated to be<br />
available.<br />
- Building A3 will no longer be a utilized as a community center; that use has been moved to<br />
a new facility on Bloomingdale.<br />
3.9.2.3 Academic Programs<br />
The Campus Committee identified some programming changes that will need to be noted in the<br />
Campus Master Plan. These include the following:<br />
- Addition of a new Biotechnology Program<br />
- Engineering Manufacturing has been Changed to Engineering Technology<br />
- Continuing Education Programs are moving to HCC Ybor Campus<br />
2010 Master Plan 39