4.3.5 Excitation System<br />
A continuous fast acting automatic excitation control system of a proven design<br />
shall be provided to control the generator voltage without hunting/instability over<br />
the entire operating range of the generator.<br />
The excitation system shall be provided with a fast-acting MVAr limiter so as to<br />
prevent the generator output falling below its safe limit. A power system<br />
stabilizer shall be incorporated in the excitation system of each generator. The<br />
Automatic Voltage Regulator (AVR) shall also be provided with but not be<br />
limited to Quadrature Droop Compensation, and Cross Current Compounding.<br />
Protection features as part of the system shall include over-voltage, overcurrent,<br />
VT fuse failure, diode failure, overfluxing, and AVR power supply failure. A<br />
field shorting or discharge switch feature shall also be included in the system as<br />
protection against overstressing the generator insulation in the event of a fault.<br />
Manual excitation control facilities shall be provided as a backup to the<br />
automatic control, and shall have an adequate range to allow for control of<br />
excitation for testing purposes. A true null balance shall be provided to allow for<br />
smooth excitation transfer between manual and automatic control.<br />
4.3.6 Power and Auxiliary Transformers<br />
The Company shall provide generator step-up, start-up, and auxiliary<br />
transformers for Facility service, including all protection, busbars, and disconnect<br />
switches as required, and transformers for all auxiliaries. The power transformer<br />
shall be equipped with on-load tap changer.<br />
4.3.7 Control and Supervision<br />
Supervision/control, monitoring and information systems shall comply with<br />
<strong>BPDB</strong>’s system control concepts and procedures and shall be subject to the<br />
approval of <strong>BPDB</strong>.<br />
Automatic and manual synchronizing facilities, with such check facilities as may<br />
be required shall be provided as a minimum for all circuits associated with<br />
generators.<br />
The Facility shall be provided with a central on-Site control room (CCR) so that<br />
operators can control the generators and perform switching and load dispatch<br />
duties. A Distributed Control System (DCS) shall be provided to coordinate the<br />
control and supervision of the generator control, Facility auxiliary systems, and<br />
generator step-up transformer breakers.<br />
Request for Proposal (<strong>Chittagong</strong> 50±10% MW HFO Fired Project) Page 63