Chittagong - BPDB
Chittagong - BPDB
Chittagong - BPDB
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
5.6 TESTS REQUIRED THROUGHOUT THE LIFE OF THE PLANT<br />
Once the Facility has been fully commissioned, <strong>BPDB</strong> will require DC tests to be<br />
undertaken every 12 months during the Term of the PPA, to demonstrate the Facility<br />
available DC. This test shall also be for a period of not less than 6 hours, as defined in<br />
Article 5.5.3 above.<br />
5.7 TEST REPORTS<br />
As soon as possible after the tests, but in no case later than one week from the end of a<br />
test, the Company shall prepare and submit to <strong>BPDB</strong> a draft Test Report. Following<br />
approval of the draft report, six copies of the final Test Report shall be submitted to<br />
<strong>BPDB</strong>. This report shall include:<br />
a. Brief description of the plant tested<br />
b. Procedure for testing and calculations<br />
c. Calculations<br />
d. Results (corrected and uncorrected)<br />
e. Correction curves<br />
f. Copy of log sheets<br />
g. Calibration certificates of all instruments<br />
All references to <strong>BPDB</strong> in the testing may well refer to PGCB, BPC or other GOB entity<br />
having proper jurisdiction.<br />
6.0 SITE DATA<br />
6.1 SITE LOCATION<br />
The Facility will be constructed at Patenga/Mohora or any other Site near to 132/33 kV<br />
Halishahar Grid Substation/33 kV Mohora Substation, <strong>Chittagong</strong>, arranged and developed by<br />
the Company.<br />
Request for Proposal (<strong>Chittagong</strong> 50±10% MW HFO Fired Project) Page 72