5.6 TESTS REQUIRED THROUGHOUT THE LIFE OF THE PLANT<br />

Once the Facility has been fully commissioned, <strong>BPDB</strong> will require DC tests to be<br />

undertaken every 12 months during the Term of the PPA, to demonstrate the Facility<br />

available DC. This test shall also be for a period of not less than 6 hours, as defined in<br />

Article 5.5.3 above.<br />

5.7 TEST REPORTS<br />

As soon as possible after the tests, but in no case later than one week from the end of a<br />

test, the Company shall prepare and submit to <strong>BPDB</strong> a draft Test Report. Following<br />

approval of the draft report, six copies of the final Test Report shall be submitted to<br />

<strong>BPDB</strong>. This report shall include:<br />

a. Brief description of the plant tested<br />

b. Procedure for testing and calculations<br />

c. Calculations<br />

d. Results (corrected and uncorrected)<br />

e. Correction curves<br />

f. Copy of log sheets<br />

g. Calibration certificates of all instruments<br />

All references to <strong>BPDB</strong> in the testing may well refer to PGCB, BPC or other GOB entity<br />

having proper jurisdiction.<br />

6.0 SITE DATA<br />

6.1 SITE LOCATION<br />

The Facility will be constructed at Patenga/Mohora or any other Site near to 132/33 kV<br />

Halishahar Grid Substation/33 kV Mohora Substation, <strong>Chittagong</strong>, arranged and developed by<br />

the Company.<br />

Request for Proposal (<strong>Chittagong</strong> 50±10% MW HFO Fired Project) Page 72