Schedule F<br />
Base prices to be considered for escalation & recoveries<br />
Sl. No Material Star Price<br />
(Rate in Figures and Words)<br />
1 For Cement as valid at the time of last<br />
stipulated date of receipt of<br />
tender and shall be intimated<br />
accordingly<br />
2(a)<br />
2(b)<br />
For Reinforcement Steel TMT bars<br />
8 and 10 mm FE 415/500<br />
For Reinforcement Steel TMT bars<br />
12 mm and above FE-415/500<br />
as valid at the time of last<br />
stipulated date of receipt of<br />
tender and shall be intimated<br />
accordingly<br />
as valid at the time of last<br />
stipulated date of receipt of<br />
tender and shall be intimated<br />
accordingly<br />
36.2.1 Subsequent Legislation<br />
If, after the date seven days prior to the latest date for submission of Bids<br />
for the Works, there occurs changes to any National or State Statute,<br />
Ordinance, Decree or other law or any regulation or bye-law of any local<br />
or other duly constituted authority or the introduction of any such statute<br />
ordinance, etc. which causes additional or reduced cost, the same shall be<br />
certified by the Engineer and shall be paid by or credited to the Employer<br />
and the Contract Price adjusted accordingly.<br />
The following items are not to be included in the price adjustment<br />
calculations:<br />
a. Liquidated Damages.<br />
b. Retention money withheld and released.<br />
c. Advance payments in the form of loan and their repayments.<br />
d. Value of any additional or varied work valued at current price.<br />
e. Payment to nominated subcontractors included as "Provisional<br />
sums" or "Prime cost" items in the Contract Price.<br />
HSCC/RIMS/2010/01 P I<br />
SCC-24