Payments to the Contractor by the Consultant shall be made in Indian Rupees into<br />
a bank account or accounts nominated by the Contractor or by account payee<br />
cheque.<br />
60.5 Retention Money<br />
A retention amounting to 10 (Ten) percent of the amounts, determined in<br />
accordance with the procedure set out in Sub-Clause 60.1 (h) shall be made by the<br />
Engineer in the first and following Interim Payment Certificates, until the amount<br />
so retained reaches a limit of retention money (5% of Contract Price) as stated in<br />
the Appendix to Tender (Annexure – D – Volume III).<br />
60.6 Payment of Retention Money<br />
(a)<br />
(b)<br />
Upon the issue of the Taking-Over Certificate with respect to the whole of<br />
the Works, one half of the Retention Money, or upon the issue of a<br />
Taking-Over Certificate with respect to a Section or part of the Permanent<br />
Works only such proportion thereof as the Engineer determines having<br />
regard to the relative value of such Section or part of the Permanent<br />
Works, shall be certified by the Engineer for payment to the Contractor.<br />
upon the expiration of the Defects Liability Period for the Works the other<br />
half of the Retention Money shall be certified by the Engineer for<br />
payment to the Contractor. Provided that, in the event of different Defects<br />
Liability Periods having become applicable to different Sections or parts<br />
of the Permanent Works pursuant to Clause 48.1 to 48.4, the expression<br />
"expiration of the Defects Liability period" shall, for the purposes of this<br />
Sub-Clause, be deemed to mean the expiration of the latest of such<br />
periods. Provided also that if at such time, there shall remain to be<br />
executed by the Contractor any work ordered, pursuant to Clauses 49.1 to<br />
49.4. and 50.1, in respect of the Works, the Engineer shall be entitled to<br />
withhold certification until completion of such work of so much of the<br />
balance of the Retention Money as shall, in the opinion of the Engineer,<br />
represent the cost of the work remaining to be executed.<br />
60.7 Advance Payment<br />
HSCC/RIMS/2010/01 PI<br />
a. The Consultant/Employer will make an advance payment at an interest @<br />
10 (Ten) Percent to the Contractor exclusively for the costs of<br />
mobilization in respect of the works in an amount equivalent to 5 (Five)<br />
percent of the contract price named in the Letter of Acceptance. Payment<br />
of such advance amount will be due under separate certification by the<br />
Engineer after (i) execution of the Form of Agreement by the Parties<br />
hereto; (ii) provision by the Contractor of the performance security in<br />
accordance with sub-clause 10.1; and (iii) provision by the Contractor of<br />
an unconditional bank guarantee in a form and by a bank acceptable to<br />
the consultant in amounts equal to the advance payment. Such bank<br />
guarantee shall remain effective until the advance payment has been<br />
repaid pursuant paragraph (b) below, but the amount thereof shall be<br />
GCC-54