(b)<br />

the amount, which shall be added to the Contract Price, in respect of the<br />

cost incurred by the Contractor by reason of such suspension.<br />

And shall notify the Contractor accordingly.<br />

40.3 Suspension lasting more than 84 Days<br />

If the progress of the Works or any part thereof is suspended on the written<br />

instructions of the Engineer and if permission to resume work is not given by the<br />

Engineer within a period of 84 days from the date of suspension then, unless such<br />

suspension is within paragraph (a), (b), (c) or (d) of Sub-Clause 40.1, the<br />

Contractor may give notice to the Engineer requesting permission, within 28<br />

days from the receipt thereof, to proceed with the Works or that part thereof in<br />

regard to which progress is suspended. If, within the said time, such permission<br />

is not granted, the Contractor may, but is not bound to, elect to treat the<br />

suspension, where it affects part only of the Works, as an omission of such part<br />

under Clause 51.1 to 51.2 by giving a further notice to the Engineer to that effect,<br />

or, where it affects the whole of the Works, treat the suspension as an event of<br />

default by the Employer and terminate his employment under the Contract in<br />

accordance with the provisions of Sub- Clause 69.1, whereupon the provisions of<br />

Sub-Clause 69.2 and 69.3 shall apply.<br />

HSCC/RIMS/2010/01 PI<br />

GCC-34