(b)<br />
the amount, which shall be added to the Contract Price, in respect of the<br />
cost incurred by the Contractor by reason of such suspension.<br />
And shall notify the Contractor accordingly.<br />
40.3 Suspension lasting more than 84 Days<br />
If the progress of the Works or any part thereof is suspended on the written<br />
instructions of the Engineer and if permission to resume work is not given by the<br />
Engineer within a period of 84 days from the date of suspension then, unless such<br />
suspension is within paragraph (a), (b), (c) or (d) of Sub-Clause 40.1, the<br />
Contractor may give notice to the Engineer requesting permission, within 28<br />
days from the receipt thereof, to proceed with the Works or that part thereof in<br />
regard to which progress is suspended. If, within the said time, such permission<br />
is not granted, the Contractor may, but is not bound to, elect to treat the<br />
suspension, where it affects part only of the Works, as an omission of such part<br />
under Clause 51.1 to 51.2 by giving a further notice to the Engineer to that effect,<br />
or, where it affects the whole of the Works, treat the suspension as an event of<br />
default by the Employer and terminate his employment under the Contract in<br />
accordance with the provisions of Sub- Clause 69.1, whereupon the provisions of<br />
Sub-Clause 69.2 and 69.3 shall apply.<br />
HSCC/RIMS/2010/01 PI<br />
GCC-34