2003 WL 21729349 Page 62003 WL 21729349 (QBD (T&CC)), [2003] EWHC 1487(Publication page references are not available for this document.)32(a) above and by reason of the same Costain isnow estopped from denying that any claim madeby <strong>Tesco</strong> is statute-barred provided that any suchclaim has been made within 12 years of theoccurrence of the relevant breach of whichcomplaint is made (which it has).(c) Further, and as Costain knew, <strong>Tesco</strong>'spolicy was to let its construction contracts only onits (<strong>Tesco</strong>'s) standard terms. By way of example,<strong>Tesco</strong> relies on its letter to Costain EngineeringConstruction Limited dated 11 June 1993."23. In paragraph 5 of PHJ's Defence to Costain'sPart 20 Particulars of Claim it was pleaded that:--"PHJ's case as to the contractual position so faras it related to <strong>Tesco</strong>, Costain and PHJ is asfollows:(i) Costain was engaged by <strong>Tesco</strong> asDesign and Build Contractors. PHJ adopts the caseadvanced by <strong>Tesco</strong> in this regard, and further aversthat by no later than 3.4.90, <strong>Tesco</strong> and Costain hadagreed upon the terms of a Design and BuildContract, in the form of the documents forwardedby Costain to Bucknall Austin on or about 26.3.90.PHJ rely in support of this averment upon, interalia, Bucknall Austin's letter to Costain dated15.3.90; Costain's letter to Bucknall Austin dated26.3.90, with its enclosures; and Bucknall Austin'sletter to Costain dated 3.4.90.(ii) Further, <strong>Tesco</strong>, Costain and PHJ eachconducted themselves, at all material times from atleast April 1989 onwards, on the commonassumption that Costain was engaged by <strong>Tesco</strong> asDesign and Build Contractors; and that PHJ wasengaged as Costain's architect. PHJ will rely insupport of this averment upon, inter alia, thefollowing facts and matters:(a) <strong>Tesco</strong>, by letter dated 4.5.89, instructedPHJ to submit all accounts to Costain, inaccordance with the Design and Build contractualdocumentation which had passed between <strong>Tesco</strong>and Costain.(b) Costain duly paid the accountstendered by PHJ.(c) Costain specifically instructed PHJ, byletter dated 11.5.89, as follows:"Any variations to existing drawings,other than those specifically requested by anofficial <strong>Tesco</strong> instruction, must be issued toourselves in preliminary form, for a cost analysisprior to issue as a construction detail."(d) Costain dealt direct with <strong>Tesco</strong> overquestions of design which arose from time to time,including, by way of example, the design of thetoilet area, as evidenced by a letter dated 19.5.89from <strong>Tesco</strong> to Costain; and the design of theCustomer Catering Facility, as evidenced by aletter dated 22.5.89 from Costain to PHJ enclosing<strong>Tesco</strong>'s drawing detailing <strong>Tesco</strong>'s instructions inrelation to the said facility;(e) Costain complained, from time to timeabout PHJ's work, as evidenced, for example, byCostain's letters to PHJ of 14.6.89 and 8.8.89.(f) Costain assumed responsibility for themanagement of the site and for the co-ordination ofall activities, including design work. PHJ will relyin this regard upon the Minutes of Site Meetings, towhich PHJ will refer for their full terms and effect.(g) Costain named <strong>Tesco</strong>'s Design andConstruct Contract Issue No. 7 as the main contractin its (Costain's) sub-contracts in respect of theRedditch store.(iii) PHJ believed, at all material times,that Costain had been engaged by <strong>Tesco</strong> as Designand Build Contractors; and acted, at all materialtimes, in reliance upon this belief. PHJ will rely,inter alia, upon the following facts and matters:(a) That PHJ would otherwise have actedas Employer's representative, and takenresponsibility for the communication of <strong>Tesco</strong>'srequirements from <strong>Tesco</strong> to Costain; and wouldhave issued Instructions to Costain, rather thanacting at Costain's direction, as was in fact the case.(b) That PHJ would have assumedresponsibility for the direction and co-ordination ofdesign sub-contractors, rather than Costain, as wasin fact the case.(c) That PHJ would otherwise haveassumed responsibility for the administration of theterms of the contract, including certifyingpayments, assessing and, where justified, grantingextensions of time, certifying Practical or PartialCompletion, and listing defects.(d) That PHJ would otherwise havechaired and minuted Site Meetings, rather thanCostain, as was in fact the case.(e) That PHJ would have held separateDesign Team meetings with <strong>Tesco</strong> and othermembers of the design team, and not left suchmatters to Costain.(iv) PHJ's belief that Costain had beenengaged by <strong>Tesco</strong> as Design and Build Contractorswas a belief induced by both <strong>Tesco</strong> and Costain. Sofar as concerns Costain, PHJ relies in support ofthis contention upon the facts and matters set outabove.(v) In the premises, and whether or notthere was in fact a Design and Build contractconcluded between Costain and <strong>Tesco</strong>, whether asalleged by <strong>Tesco</strong> or otherwise, it is averred thatCostain is estopped, by convention and/or conduct,as against PHJ and/or <strong>Tesco</strong>, from denying that itwas retained by <strong>Tesco</strong> as a Design and BuildContractor on <strong>Tesco</strong>'s Design and ConstructContract Issue No. 7; alternatively is estopped fromdenying that it undertook the obligations of aDesign and Build contractor in relation to theRedditch store.Copr. © West 2004 No Claim to Orig. Govt. Works
2003 WL 21729349 Page 72003 WL 21729349 (QBD (T&CC)), [2003] EWHC 1487(Publication page references are not available for this document.)(vi) It is further averred that PHJ'scontractual obligations were in fact transferred bynovation from <strong>Tesco</strong> to Costain, in accordance withthe Design and Build arrangements set out above.In this regard, PHJ says further as follows:(a) PHJ did in fact, on 4.5.90, execute anovation agreement, as had been contemplated inthe letter to PHJ dated 22.2.89, pursuant to whichits contractual obligations were purportedlytransferred from <strong>Tesco</strong> to Costain. This documentwas not so far as PHJ can now ascertain, everexecuted by either <strong>Tesco</strong> or Costain.(b) It is, however, PHJ's case that therewas a novation by conduct, in about April 1989, asa result of which PHJ's contractual obligations werein fact transferred from <strong>Tesco</strong> to Costain.(c) Further or alternatively, it is averredthat <strong>Tesco</strong>, Costain and PHJ each conductedthemselves, at all material times from April 1989onwards, on the common assumption that there hadbeen such a novation; on the common assumptionthat Costain was engaged by <strong>Tesco</strong> as Design andBuild Contractors; and on the common assumptionthat PHJ was engaged as Costain's architect. PHJwill rely in support of each of these avermentsupon, inter alia, the facts and matters set out above.(d) In the premises, <strong>Tesco</strong> and Costain areeach now estopped by convention, or by conduct,from denying that there was such a novation at orabout that time."24. During the course of the hearing before me<strong>Tesco</strong> sought and obtained, again withoutobjection, permission further to amend its Re-Amended Reply to the Defence of Costain and theOther Costain Company in Action 07 so as to addthese paragraphs in relation to the course of dealingupon which <strong>Tesco</strong> sought to rely:--"4A. Paragraph 12 is denied. It was not anessential pre-requisite or condition precedent ofCostain taking on contractual or any other legalresponsibility for the design or of there being alegally binding contract between Costain and<strong>Tesco</strong>, that Costain were to receive executednovation agreements in respect of the consultants atthe same time as and as part of the execution of theformal contract documents between Costain and<strong>Tesco</strong>. No such precondition was intimated by<strong>Tesco</strong> to Costain, let alone agreed between theparties.4B. Further, and as Costain had demonstrated atother projects where the contract documentationwas executed prior to Costain commencing work atRedditch, Costain was perfectly prepared toexecute the contract documents as between itselfand <strong>Tesco</strong> in the absence of some or all of thenovation agreements (whether executed or not). Forthe avoidance of doubt, <strong>Tesco</strong> will contend that thisdemonstrates that the receipt of executed novationscannot have been a precondition for Costainconcluding a binding contract with <strong>Tesco</strong> underwhich Costain took responsibility for the design ofthe store. In this regard <strong>Tesco</strong> relies on thefollowing projects:(1) Mold(2) Crick(3) Pontypridd4C. In each of the projects referred to inparagraph 4B above, Costain executed the contractdocuments as between itself and <strong>Tesco</strong> in theabsence of executed novation agreements in respectof one or more of the consultants.4D. <strong>Tesco</strong> relies on this course of dealingbetween the parties as demonstrating that there wasno essential pre-requisite or condition precedent ofthe type alleged in paragraph 12."25. It is not material for the purposes of thisjudgment to set out more precisely than I havealready the nature of the alleged breaches ofcontract for which <strong>Tesco</strong> contended or the nature ofthe alleged negligence on the part of Costain inperforming its obligations as a result of that allegedcontract.26. As I have already indicated, the other matterscomplained of as against Costain on behalf of<strong>Tesco</strong>, apart from failure to perform properlyobligations allegedly assumed in relation to theconstruction of the Store in the first place, concernthe alleged inspection of the Store by Costain inOctober 1993 and the reports made of the results ofthat inspection. The case as against Costain was putin the Re-Amended Particulars of Claim in Action07 in this way:--"21. On the evening of 17 July 1993, <strong>Tesco</strong>'sstore in Maidstone, Kent was substantiallydestroyed by fire. The fire had been starteddeliberately by persons unknown in a plastic refusebin outside a newsagents, which was part of thesame shopping complex as the Maidstone store.The fire penetrated the interior of the roof of thenewsagents through the timber soffit, and thenspread through the roof void of the entire complex.22. As a consequence of such fire, <strong>Tesco</strong> tooksteps to check that the works necessary to inhibitthe spread of fire had been carried out at otherstores constructed to a similar design.23. On 19 October 1993, Costain who knew, as aresult of their extensive links with <strong>Tesco</strong>, of<strong>Tesco</strong>'s desire to check the extent of fire inhibitingworks at other stores, wrote to <strong>Tesco</strong> in thefollowing terms in relation to the Redditch store,"Although we did not receive a letterspecific to this store, we have taken it uponourselves to carry out a detailed inspection of firebarriers as per other stores constructed by ourCompany in the Midlands.Copr. © West 2004 No Claim to Orig. Govt. Works
- Page 1 and 2: 2003 WL 21729349 Page 12003 WL 2172
- Page 3 and 4: 2003 WL 21729349 Page 32003 WL 2172
- Page 5: 2003 WL 21729349 Page 52003 WL 2172
- Page 9 and 10: 2003 WL 21729349 Page 92003 WL 2172
- Page 11 and 12: 2003 WL 21729349 Page 112003 WL 217
- Page 13 and 14: 2003 WL 21729349 Page 132003 WL 217
- Page 15 and 16: 2003 WL 21729349 Page 152003 WL 217
- Page 17 and 18: 2003 WL 21729349 Page 172003 WL 217
- Page 19 and 20: 2003 WL 21729349 Page 192003 WL 217
- Page 21 and 22: 2003 WL 21729349 Page 212003 WL 217
- Page 23 and 24: 2003 WL 21729349 Page 232003 WL 217
- Page 25 and 26: 2003 WL 21729349 Page 252003 WL 217
- Page 27 and 28: 2003 WL 21729349 Page 272003 WL 217
- Page 29 and 30: 2003 WL 21729349 Page 292003 WL 217
- Page 31 and 32: 2003 WL 21729349 Page 312003 WL 217
- Page 33 and 34: 2003 WL 21729349 Page 332003 WL 217
- Page 35 and 36: 2003 WL 21729349 Page 352003 WL 217
- Page 37 and 38: 2003 WL 21729349 Page 372003 WL 217
- Page 39 and 40: 2003 WL 21729349 Page 392003 WL 217
- Page 41 and 42: 2003 WL 21729349 Page 412003 WL 217
- Page 43 and 44: 2003 WL 21729349 Page 432003 WL 217
- Page 45 and 46: 2003 WL 21729349 Page 452003 WL 217
- Page 47 and 48: 2003 WL 21729349 Page 472003 WL 217
- Page 49 and 50: 2003 WL 21729349 Page 492003 WL 217
- Page 51 and 52: 2003 WL 21729349 Page 512003 WL 217
- Page 53 and 54: 2003 WL 21729349 Page 532003 WL 217
- Page 55 and 56: 2003 WL 21729349 Page 552003 WL 217
- Page 57 and 58:
2003 WL 21729349 Page 572003 WL 217
- Page 59 and 60:
2003 WL 21729349 Page 592003 WL 217
- Page 61 and 62:
2003 WL 21729349 Page 612003 WL 217
- Page 63 and 64:
2003 WL 21729349 Page 632003 WL 217
- Page 65 and 66:
2003 WL 21729349 Page 652003 WL 217
- Page 67 and 68:
2003 WL 21729349 Page 672003 WL 217
- Page 69 and 70:
2003 WL 21729349 Page 692003 WL 217
- Page 71 and 72:
2003 WL 21729349 Page 712003 WL 217
- Page 73 and 74:
2003 WL 21729349 Page 732003 WL 217
- Page 77 and 78:
2003 WL 21729349 Page 772003 WL 217
- Page 79 and 80:
2003 WL 21729349 Page 792003 WL 217
- Page 81 and 82:
2003 WL 21729349 Page 812003 WL 217
- Page 83 and 84:
2003 WL 21729349 Page 832003 WL 217
- Page 85 and 86:
2003 WL 21729349 Page 852003 WL 217
- Page 87 and 88:
2003 WL 21729349 Page 872003 WL 217
- Page 89 and 90:
2002 WL 347140 Page 12002 WL 347140
- Page 91 and 92:
2002 WL 347140 Page 32002 WL 347140
- Page 93 and 94:
2002 WL 347140 Page 52002 WL 347140
- Page 95 and 96:
2002 WL 347140 Page 72002 WL 347140
- Page 97 and 98:
2002 WL 347140 Page 92002 WL 347140
- Page 99 and 100:
2002 WL 347140 Page 112002 WL 34714
- Page 101 and 102:
2002 WL 347140 Page 132002 WL 34714
- Page 103 and 104:
2002 WL 347140 Page 152002 WL 34714
- Page 105 and 106:
2002 WL 347140 Page 172002 WL 34714
- Page 107 and 108:
2002 WL 347140 Page 192002 WL 34714
- Page 109 and 110:
2002 WL 347140 Page 212002 WL 34714
- Page 111 and 112:
2002 WL 347140 Page 232002 WL 34714
- Page 113 and 114:
2002 WL 347140 Page 252002 WL 34714
- Page 115 and 116:
1990 S.L.T. 249 Page 11989 WL 98434
- Page 117 and 118:
1990 S.L.T. 249 Page 31989 WL 98434
- Page 119 and 120:
1990 S.L.T. 249 Page 51989 WL 98434
- Page 121 and 122:
1990 S.L.T. 249 Page 71989 WL 98434
- Page 123 and 124:
1984 S.L.T. 100 Page 21983 WL 21732
- Page 125 and 126:
1984 S.L.T. 100 Page 41983 WL 21732
- Page 127 and 128:
1984 S.L.T. 100 Page 61983 WL 21732
- Page 129 and 130:
1984 S.L.T. 100 Page 81983 WL 21732
- Page 131 and 132:
1984 S.L.T. 100 Page 101983 WL 2173
- Page 133 and 134:
[1961] 1 Q.B. 31 Page 21960 WL 1892
- Page 135 and 136:
[1961] 1 Q.B. 31 Page 41960 WL 1892
- Page 137 and 138:
[1961] 1 Q.B. 31 Page 61960 WL 1892
- Page 139 and 140:
[1961] 1 Q.B. 31 Page 81960 WL 1892
- Page 141 and 142:
[1961] 1 Q.B. 31 Page 101960 WL 189
- Page 143 and 144:
[1961] 1 Q.B. 31 Page 121960 WL 189
- Page 145 and 146:
[1961] 1 Q.B. 31 Page 141960 WL 189
- Page 147 and 148:
[1961] 1 Q.B. 31 Page 161960 WL 189
- Page 149 and 150:
[1961] 1 Q.B. 31 Page 181960 WL 189
- Page 151 and 152:
[1961] 1 Q.B. 31 Page 201960 WL 189
- Page 153 and 154:
[1961] 1 Q.B. 31 Page 221960 WL 189
- Page 155 and 156:
[1961] 1 Q.B. 31 Page 241960 WL 189
- Page 157 and 158:
[1961] 1 Q.B. 31 Page 261960 WL 189
- Page 159 and 160:
[1961] 1 Q.B. 31 Page 281960 WL 189
- Page 161 and 162:
[1961] 1 Q.B. 31 Page 301960 WL 189
- Page 163 and 164:
(1923) 16 Ll. L. Rep. 325 Page 2192
- Page 165 and 166:
[1912] 2 Ch. 125 Page 21912 WL 1739
- Page 167 and 168:
[1912] 2 Ch. 125 Page 41912 WL 1739
- Page 169 and 170:
[1912] 2 Ch. 125 Page 61912 WL 1739
- Page 171 and 172:
[1912] 2 Ch. 125 Page 81912 WL 1739
- Page 173 and 174:
[1912] 2 Ch. 125 Page 101912 WL 173
- Page 175 and 176:
[1912] 2 Ch. 125 Page 121912 WL 173
- Page 177 and 178:
[1912] 2 Ch. 134 Page 21909 WL 1582
- Page 179 and 180:
[1912] 2 Ch. 134 Page 41909 WL 1582
- Page 181 and 182:
[1912] 2 Ch. 134 Page 61909 WL 1582
- Page 183 and 184:
(1883) L.R. 22 Ch. D. 441 Page 2188
- Page 185 and 186:
(1883) L.R. 22 Ch. D. 441 Page 4188
- Page 187 and 188:
(1883) L.R. 22 Ch. D. 441 Page 6188
- Page 189 and 190:
(1879-80) L.R. 5 Q.B.D. Page 21879
- Page 191 and 192:
(1879-80) L.R. 5 Q.B.D. Page 41879
- Page 193 and 194:
JBL 1987, Mar, 122-130 Page 1(Cite
- Page 195 and 196:
JBL 1987, Mar, 122-130 Page 3(Cite
- Page 197 and 198:
JBL 1987, Mar, 122-130 Page 5(Cite
- Page 199 and 200:
JBL 1987, Mar, 122-130 Page 7(Cite