Procurement SchedulingNormal construction contract schedules should be established that allow adequatedesign and plan preparation time, design and review approval, contractpreparation, advertising and award, and construction time. A typical pavementproject is designed 1 to 2 years before it is constructed; however, plans andspecifications for relatively small projects can be completed within a few months.Once construction is completed, the new RMP surfacing usually achieves fullstrength in about 21 days, but it may be opened to pedestrian traffic in 24 hr andlight automobile traffic in 3 days.G - 34