12.07.2015 Views

Storm Water Pollution Prevention Plan (SWPPP) - the City of Lompoc!

Storm Water Pollution Prevention Plan (SWPPP) - the City of Lompoc!

Storm Water Pollution Prevention Plan (SWPPP) - the City of Lompoc!

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Receiving <strong>Water</strong>: HighThe Santa Ynez River is on <strong>the</strong> impaired waterbody 303d list for sedimentation/siltation, and has beneficialuses <strong>of</strong> Cold water Fishery, Migratory, and Spawning. Based on <strong>the</strong>se characteristics, <strong>the</strong> site has a highreceiving water risk.In accordance with <strong>the</strong> chart below, <strong>the</strong> project was determined to have a combined Level 2 Risk based on itssediment (low) and receiving water (high) characteristics. A copy <strong>of</strong> <strong>the</strong> Risk Assessment is provided inAppendix D.The General Permit requires visual monitoring at all sites, and effluent water quality at all Risk Level 2 & 3.Section 4 elaborates on <strong>the</strong> required monitoring for this project. This <strong>SWPPP</strong> is designed to adhere to RiskLevel 2 requirements as established in Attachment D <strong>of</strong> <strong>the</strong> General Permit.Transmission <strong>Water</strong> MainThe Transmission <strong>Water</strong> Main will be installed primarily along existing paved roads. In addition, disturbedareas will be returned to pre-construction conditions at project completion. Using <strong>the</strong> LUP Project TypeDetermination Flow Chart in Attachment A.1 <strong>of</strong> <strong>the</strong> Permit, <strong>the</strong> project is considered a Type 1 LUP. However,because this is a combined <strong>SWPPP</strong> <strong>the</strong> higher risk level <strong>of</strong> <strong>the</strong> two portions <strong>of</strong> <strong>the</strong> project was utilized. Type 2LUP requirements will be met for <strong>the</strong> linear portion <strong>of</strong> <strong>the</strong> project.2.7 Construction ScheduleThe project is anticipated to start in <strong>the</strong> fall <strong>of</strong> 2010 and be completed prior to <strong>the</strong> rainy season.Contract Award 01/01/2011Site Preparation and Grubbing 01/01/2011Implement Temporary Erosion and Sediment Control BMPs 01/08/2011Clearing and Grading 01/10/2011Well Drilling 01/15/2011Electrical conduit/ subgrade preparation 01/27/2011Transmission <strong>Water</strong> Main Line 02/20/2011PCC and Drainage 02/27/2011AC Paving Operations 02/27/11Slope Stabilization 08/10/2011Project Accepted 08/15/20112.8 Potential Construction Site Pollutant SourcesThe following is a list <strong>of</strong> construction materials which will be used and activities that will be performed thathave <strong>the</strong> potential to contribute pollutants <strong>of</strong>f-site:• Clearing, Grubbing, Trenching and Grading Operations (slopes, pads, driveway and pipeline)• Base and AC Pavement Placement (driveway and pipeline)• PCC (curbs and pads)• Vehicle fluids, including oil, grease, petroleum and coolants (from construction equipment)• Trash (from construction personnel)Municipal <strong>Water</strong> Well No. 11 and Transmission <strong>Water</strong> Main – <strong>SWPPP</strong> July 20, 2010Page 8

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!