• install branch nipple flange;• install isolation valve;• remove habitat;• install “hot tap” machine;• perform “hot tap”;• remove “hot tap” machine; and• install “hot tap” protection structure.“Mechanical” hot tap activities can be described as follows:• expose buried pipeline section by airlifting sediments;• remove weight and corrosion coating;• inspect pipeline;• install mechanical clamp;• install “hot tap” machine;• perform “hot tap”;• remove “hot tap” machine; and• install “hot tap” protection structure.The “hot tap” structure is connected via a spool piece to a <strong>Deep</strong> <strong>Panuke</strong> tie-in structure which houses theequipment that will be required at the end of the <strong>Deep</strong> <strong>Panuke</strong> export pipeline. This equipment includesa manual isolation valve, a check valve and provision for a temporary subsea pig receiver. A protectionstructure will be placed around each of the SOEP pipeline hot tap equipment and the <strong>Deep</strong> <strong>Panuke</strong>pipeline tie-in equipment.Refer to Section 2.3.5 which provides additional detail on methods involving sediment disposal withrespect to the hot tap installation.2.3.4 Subsea Flowlines and UmbilicalsA total of six to nine subsea flowlines will be installed on the seafloor to tie-in the five to eight productionwells and one injection well. It is expected that the subsea production flowlines will be 200 to 250 mm [8to 10 inches] in diameter and range from 1 to approximately 10 km in length. The injection flowline isexpected to be 75 mm [3 inches] in diameter and approximately 1.7 km in length. The flowlines may be aflexible or rigid design and may be installed by reel-lay or s-lay pipelay methods. The flowlines will betrenched and buried. Flowline lengths, diameters, and installation method will be confirmed during detaileddesign.<strong>Deep</strong> <strong>Panuke</strong> Volume 4 (Environmental Assessment Report)• November 2006 2-17

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!