2.3.8.1 Drilling Fluid ProgramWater-based muds (WBM) will be used in development drilling. These muds are used to protect andclean the drill hole, for overbalancing formation pressures, and for bringing cuttings to the surface. Theselection of the drilling fluid is based on factors such as the hole angle, the formation types drilled(mudstone, sandstone, clays, etc.), and the time of exposure.WBM is a suspension of solids and dissolved material in a carrier base fluid of water. WBM tends to beused for wells that are normally pressured or do not encounter difficult geology. Based on theexperience gained while drilling the <strong>Deep</strong> <strong>Panuke</strong> delineation wells, it was determined that only WBMwill be used for any new development drilling activities.The typical composition of WBM (seawater gel mud type) for <strong>Deep</strong> <strong>Panuke</strong> are as follows:• barite;• bentonite;• potassium chloride (KCl);• polymers;• water;• glycol;• soda ash/sodium bicarbonate/lime;• caustic soda; and• salt (sodium chloride or calcium chloride).During drilling of the new wells, the mud is circulated down the drillpipe from the drilling unit to thebottom of the wellbore and returned to the drilling unit in the annular space (between drill pipe and openhole/casing) carrying the cuttings from the well. Each hole section of a wellbore requires different fluidproperties. Thus after each hole section, the mud is modified or changed out. WBM that is no longerrequired will be disposed of overboard, along with WBM cuttings in accordance with the OffshoreWaste Treatment Guidelines (OWTG) (NEB et al. 2002).For the wells to be re-entered and completed, some drilling is required to remove cement suspensionplugs. This will be done using a viscosified brine solution and so traditional drilling mud will not berequired. Prior to removal of the last suspension plug on the existing wells, the well will be displacedwith filtered completion brine which will act as an overbalanced annulus fluid for setting the productionpacker. Some viscous pills of polymer gelled brine may be used to ensure removal of all solid particlesin the wellbore. The completion fluid will be clear brine with additives for corrosion and oxygeninhibition as well as H 2 S scavengers.<strong>Deep</strong> <strong>Panuke</strong> Volume 4 (Environmental Assessment Report)• November 2006 2-28

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!