Comprehensive Report
GPO-DUELFERREPORT-3
GPO-DUELFERREPORT-3
- No tags were found...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
• Clear operating instructions to be displayed on the<br />
trailer,<br />
• Trailer needs to be lightly armored (shrapnel proof),<br />
• 2 x powder fire extinguishers are required<br />
(6kg total),<br />
• It would be possible to make a smaller version<br />
(enhanced mobility)—if the various pieces of<br />
equipment needed could be procured.SERgsT<br />
Evaluation of the Documents Pertaining to the<br />
Trailers Recovered from the Al Kindi General<br />
Establishment<br />
Republican Guard urging them to collect the completed<br />
equipment. They did not do so. Al Kindi was<br />
still assembling the second trailer when OIF started.<br />
Both trailers remained at Al Kindi at the start of OIF.<br />
On 19 April 2003 the first trailer, with its equipment<br />
largely intact, was recovered from looters and<br />
exploited by Coalition personnel. On 11 May 2003,<br />
the second trailer was recovered from Al Kindi. It<br />
appeared to have suffered some looting. It too was<br />
exploited by Coalition personnel.<br />
The exploitation effort included visiting Al Kindi.<br />
Managers, engineers, and scientists who had been<br />
involved in the project were debriefed. They provided<br />
copies of supporting documents. The equipment was<br />
measured, photographed, and samples taken of material<br />
within the first system.<br />
Summary<br />
Al Kindi and the Republican Guard Command<br />
signed a contract on 23 June 2001 under which Al<br />
Kindi would produce two hydrogen generating units<br />
for what was described as weather air stations for<br />
50,000,000 Iraqi Dinars. Work was scheduled to last<br />
16 months from 1 July 2001 to 1 November 2002.<br />
Work went more slowly than planned. Al Kindi<br />
blamed the State Enterprise for Heavy Equipments<br />
Engineering (SEHEE) in Baghdad, the sub-contractor<br />
that fabricated the reactor vessels. There were<br />
discussions concerning the provision of towing<br />
vehicles, an item missing from the original contract.<br />
Al Kindi failed to achieve the contract completion<br />
date in November 2002, and informed the Republican<br />
Guard of a six-month delay. In December 2002,<br />
in its semi-annual declaration to the UN, Al Kindi<br />
listed the ‘production station for H2 gas’ along with<br />
many other projects then on hand. The first of the<br />
two trailer-borne units was completed in early 2003.<br />
A joint Al Kindi and Republican Guard group tested<br />
the system on 11 March 2003. They concluded that,<br />
although the equipment produced hydrogen according<br />
to the specifications, there were many unsatisfactory<br />
features. Despite this, in late March 2003, the<br />
Military Industrial Commission (MIC) wrote to the<br />
Documents<br />
Al Kindi provided a dozen documents and working<br />
notes. This material was translated and analyzed. For<br />
ease of understanding this material is presented as a<br />
chronology:<br />
23 June 2001. Contract No. 73/MD/RG/2001 for the<br />
fabrication of 2 hydrogen generation units is issued at<br />
a total cost of 500,000,000 Iraqi Dinars. The specifications<br />
are listed.<br />
July 2001. Start date of Al Kindi contract for the<br />
production of the trailers.<br />
5 February 2002. Al Kindi letter to Republican Guard<br />
discussing use of small towing vehicle to pull trailers.<br />
15 October 2002. Al Kindi letter to Republican Guard<br />
informing them of late running of contract.<br />
After 15 October 2002. Undated chart labeled Technical<br />
Progress.<br />
1 November 2002. Theoretical end date of contract—<br />
6-month extension requested.<br />
15 December 2002. Al Kindi mentions the station for<br />
generating hydrogen gas for a semi-annual declaration<br />
to UNMOVIC.<br />
Biological<br />
93