14.09.2015 Views

Comprehensive Report

GPO-DUELFERREPORT-3

GPO-DUELFERREPORT-3

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

• Clear operating instructions to be displayed on the<br />

trailer,<br />

• Trailer needs to be lightly armored (shrapnel proof),<br />

• 2 x powder fire extinguishers are required<br />

(6kg total),<br />

• It would be possible to make a smaller version<br />

(enhanced mobility)—if the various pieces of<br />

equipment needed could be procured.SERgsT<br />

Evaluation of the Documents Pertaining to the<br />

Trailers Recovered from the Al Kindi General<br />

Establishment<br />

Republican Guard urging them to collect the completed<br />

equipment. They did not do so. Al Kindi was<br />

still assembling the second trailer when OIF started.<br />

Both trailers remained at Al Kindi at the start of OIF.<br />

On 19 April 2003 the first trailer, with its equipment<br />

largely intact, was recovered from looters and<br />

exploited by Coalition personnel. On 11 May 2003,<br />

the second trailer was recovered from Al Kindi. It<br />

appeared to have suffered some looting. It too was<br />

exploited by Coalition personnel.<br />

The exploitation effort included visiting Al Kindi.<br />

Managers, engineers, and scientists who had been<br />

involved in the project were debriefed. They provided<br />

copies of supporting documents. The equipment was<br />

measured, photographed, and samples taken of material<br />

within the first system.<br />

Summary<br />

Al Kindi and the Republican Guard Command<br />

signed a contract on 23 June 2001 under which Al<br />

Kindi would produce two hydrogen generating units<br />

for what was described as weather air stations for<br />

50,000,000 Iraqi Dinars. Work was scheduled to last<br />

16 months from 1 July 2001 to 1 November 2002.<br />

Work went more slowly than planned. Al Kindi<br />

blamed the State Enterprise for Heavy Equipments<br />

Engineering (SEHEE) in Baghdad, the sub-contractor<br />

that fabricated the reactor vessels. There were<br />

discussions concerning the provision of towing<br />

vehicles, an item missing from the original contract.<br />

Al Kindi failed to achieve the contract completion<br />

date in November 2002, and informed the Republican<br />

Guard of a six-month delay. In December 2002,<br />

in its semi-annual declaration to the UN, Al Kindi<br />

listed the ‘production station for H2 gas’ along with<br />

many other projects then on hand. The first of the<br />

two trailer-borne units was completed in early 2003.<br />

A joint Al Kindi and Republican Guard group tested<br />

the system on 11 March 2003. They concluded that,<br />

although the equipment produced hydrogen according<br />

to the specifications, there were many unsatisfactory<br />

features. Despite this, in late March 2003, the<br />

Military Industrial Commission (MIC) wrote to the<br />

Documents<br />

Al Kindi provided a dozen documents and working<br />

notes. This material was translated and analyzed. For<br />

ease of understanding this material is presented as a<br />

chronology:<br />

23 June 2001. Contract No. 73/MD/RG/2001 for the<br />

fabrication of 2 hydrogen generation units is issued at<br />

a total cost of 500,000,000 Iraqi Dinars. The specifications<br />

are listed.<br />

July 2001. Start date of Al Kindi contract for the<br />

production of the trailers.<br />

5 February 2002. Al Kindi letter to Republican Guard<br />

discussing use of small towing vehicle to pull trailers.<br />

15 October 2002. Al Kindi letter to Republican Guard<br />

informing them of late running of contract.<br />

After 15 October 2002. Undated chart labeled Technical<br />

Progress.<br />

1 November 2002. Theoretical end date of contract—<br />

6-month extension requested.<br />

15 December 2002. Al Kindi mentions the station for<br />

generating hydrogen gas for a semi-annual declaration<br />

to UNMOVIC.<br />

Biological<br />

93

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!