• Between Montpellier and Perpignan capacity issues could become critical at the<br />

latest once all connections to Spanish seaport, industrial plants and the other<br />

logistic terminals will be upgraded at UIC gauge. The new line will become<br />

necessary to realize the potential demand of the Corridor, clearly aiming at a<br />

strong development of rail freight transport on this axis.<br />

• Given the present traffic and its potential development, the upgrade of the line<br />

between Divača and Koper is an absolute priority: there are 82 trains/day on<br />

this single-track line, with an expected increase to 142 trains per day by 2030.<br />

The issues presented above, are being currently faced by <strong>Mediterranean</strong> Stakeholders<br />

and, in large majority, taken into due consideration in the definition of the Corridor<br />

Project list.<br />