ITALY<br />
Current Status<br />
The most relevant critical issues related to the Italian sections and nodes of the Corridor<br />
are presented hereunder:<br />
a) the missing HS railway link between Turin and Lyon<br />
b) the low standards of the conventional lines Turin-Lyon and Venice-Trieste<br />
that penalise especially the freight trains in terms of productivity<br />
c) the existing limitations to train length (400 to 600m) does not allow, in the<br />
most part of the Italian corridor, the operation of freight trains with the maximum<br />
interoperable length of 740 m., which penalizes rail transportation<br />
competitiveness<br />
d) the lack of capacity on the railway line Treviglio-Brescia and Brescia – Verona –<br />
Venezia section<br />
e) the loading gauge restriction on the conventional railway lines: Italian/French<br />
border up to Pioltello (limited to PC45)<br />
f) the urban nodes of Venice, Turin, and Milan that are characterized by a high<br />
promiscuity of rail traffic due to overlapping of metropolitan, regional, long<br />
distance and freight traffic<br />
g) the urban node of Milan is characterized by intense traffic flows, in particular<br />
crossing flows and long distance flows, causing congestion in particular in ring<br />
roads around the town<br />
h) the need of upgrading road and rail last mile links to the port facilities of<br />
Venice, Trieste and Ravenna<br />
i) Missing rail last mile links to the main airports of Milano Linate, Milano<br />
Malpensa and Milano - Bergamo Orio al Serio<br />
j) the conventional rail lines are not currently equipped with the ERTMS<br />
signalling system<br />
k) With respect to inland waterways: limited draught subject to seasonal<br />
variations, limited accessibility of the western part of the Corridor due to a<br />
missing lock and the low navigability reliability due to the constant variations in<br />
the hydraulic conditions.<br />
On-going and planned main interventions<br />
The following map depicts the matching between the detected critical issues and the ongoing<br />
and/or planned interventions reported in the Corridor Project list.<br />
Between these, concerning railway projects, the ones with the biggest KPI contribution<br />
have been selected and presented in the following map. As specified in the legend, all<br />
those cases in which works are not yet planned or agreed for completion by 2030 are<br />
marked in red.<br />