Current status<br />
The most relevant critical issues are related to:<br />
a) the existing limitations to train length (360 to 600m) on all the sections<br />
belonging to the Corridor, especially on the stretch from Rijeka up to Zagreb,<br />
where maximum admissible train length is limited to 360 meters<br />
b) the only railway lines that allow train speed above 100 km/h are Dugo Selo-<br />
Koprivnica and Moravice-Ogulin<br />
c) the urban node of Zagreb suffers from a lack of capacity in the short-medium<br />
term<br />
d) rail last mile interconnections to Rijeka Port shall be enhanced; in particular<br />
Zagreb-Rijeka railway line suffers from low technical standards with unfavourable<br />
route characterised by hard ascents, sharp and low radiant curves<br />
e) the missing railway last mile connection to Zagreb airport<br />
f) the entire Corridor railway alignment in Croatia is not equipped with ERTMS,<br />
the available signalling system is APS.<br />
On-going and planned main interventions<br />
The following map below shows the matching between the detected critical issues and<br />
the on-going and/or planned interventions.<br />
6<br />
5<br />
Rijeka<br />
L<br />
4<br />
8<br />
L<br />
L<br />
2<br />
L<br />
3<br />
L<br />
1<br />
Zagreb<br />
7<br />
CROATIA<br />
Rail: Compliance by 2030<br />
Compliant (Status 2015)<br />
Works on - going, compliance expected<br />
Works still to be to started, compliance expected<br />
Works foreseen but delayed, compliance doubted<br />
Works not yet planned/agreed for completion<br />
Reason f or non - compliance<br />
E No ‘Electrification’<br />
L ‘Line speed < 100 km/h’<br />
A ‘Axle load < 22.5 tonnes’<br />
G<br />
‘UIC gauge ? 1,435 mm’<br />
Status: June 2016<br />
Figure 16 –Croatian sections compliance by 2030 and main project impacting on KPI<br />
39