of doubt, the Buyer shall be liable for all costs resulting from any delays in loading<br />
the Product hereunder due to failure by the Buyer to supply such information in<br />
a timely manner). The Seller shall have the right to issue its own instructions if<br />
such instructions are not so provided by the Buyer.<br />
All costs (including but not limited to demurrage) arising out of any failure by the Buyer to<br />
comply with the foregoing shall be for the Buyer’s account.<br />
11.4 Substitution of Vessels<br />
In respect of any Vessel named in the nomination, the Seller shall be entitled to substitute<br />
therefore another Vessel provided always that:<br />
11.4.1 the size of the substitute Vessel and the quantity to be loaded shall not, without<br />
the prior written consent of the Buyer, differ materially from the size of the Vessel<br />
previously named and the quantity specified in the nomination; and<br />
11.4.2 the Seller shall give to the Buyer notice in writing of the name of the substitute<br />
Vessel not less than 3 clear days before:<br />
11.4.2.1 in the case of delivery CFR or CIF, the last day of the Loading Terminal<br />
Laydays of the substitute Vessel or the last day of the Loading Terminal<br />
Laydays of the Vessel originally nominated, whichever is the earlier,<br />
provided always that such substitution shall not be allowed after<br />
commencement of loading of the Vessel originally nominated unless<br />
otherwise specifically agreed between the parties; or<br />
11.4.2.2 in the case of delivery Ex Ship, the ETA of the substitute Vessel or the<br />
ETA of the Vessel originally nominated, whichever is the earlier.<br />
11.5 Acceptance of Vessels<br />
11.5.1 Notwithstanding anything to the contrary express or implied elsewhere, the<br />
Buyer shall have the right (which right may only be exercised prior to the passing<br />
of risk and property hereunder) to refuse, on any reasonable ground, to accept<br />
any Vessel named pursuant to Sections 11.2 including any Vessel referred to in<br />
Section 11.2.(g) even though such Vessel is not the performing Vessel under the<br />
Agreement, or 11.4. The Buyer shall not be liable for any loss or damage, direct<br />
or indirect, which the Seller may suffer as a result of the Buyer exercising such<br />
right.<br />
11.5.2 Notwithstanding any prior acceptance of a Vessel (whether named in the Special<br />
Provisions or nominated or substituted pursuant to Sections 11.2 or 11.4), the<br />
Buyer shall have the right (which right may only be exercised prior to the passing<br />
of risk and property hereunder) to reject the Vessel in question on any reasonable<br />
ground if such Vessel is involved in any incident or more recent information<br />
regarding such Vessel becomes available to the Buyer at any time after such prior<br />
acceptance.<br />
11.5.3 If the facilities at the Loading Terminal in question require the Seller’s Vessel to<br />
be loaded from a floating storage facility, lighter or other Vessel by means of shipto-ship<br />
transfer, such Berth shall be subject to the Buyer’s ship or Loading<br />
Terminal vetting procedures and the Buyer may, on any reasonable ground and<br />
without liability, refuse the use of such facility for the purpose of loading the<br />
nominated Vessel.<br />
11.5.4 Without derogating from any other reasonable grounds that may be available to<br />
the Buyer, in those cases where <strong>BP</strong> is the Buyer it shall be a reasonable ground<br />
for <strong>BP</strong> to reject or refuse a Vessel pursuant to this Section if the Vessel either at<br />
the time of nomination or subsequently at any time up to the time of loading is<br />
not approved by <strong>BP</strong> Ship Vetting or alternatively is determined by <strong>BP</strong> Ship Vetting<br />