06.02.2020 Views

STEEL + TECHNOLOGY 01/2020 EXTRACT

STEEL + TECHNOLOGY 01/2020 EXTRACT

STEEL + TECHNOLOGY 01/2020 EXTRACT

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>STEEL</strong> <strong>TECHNOLOGY</strong> | 39<br />

kg of ladle well filler. To examine the<br />

applied ladle well filler in the well block,<br />

this took place at the end of the refractory<br />

linings lifespan and the well block was<br />

carefully recovered at the start of the relining<br />

process. Figure 3 shows the ladle well<br />

filler covered backup well block.<br />

Result of the ideal application of ladle<br />

well filler is a material cone, peaking 15-18<br />

cm above the ladle bottom. Figure 4 illustrated<br />

the backup well block after the application<br />

of ladle well filler.<br />

After the application of ladle well filler<br />

to the backup system, the steel ladle went<br />

through a routine production cycle lasting<br />

approximately 3-4 hours and tapping via<br />

the main slide gate system. After tapping,<br />

remaining slag was poured out and the<br />

ladle was then transported to the relining<br />

facility to cool. Subsequently the worn<br />

refractory lining was removed and the<br />

backup well block was recovered. During<br />

the removal of the well block from the bottom<br />

lining, flowable ladle well filler was<br />

lost and only solidified structures could be<br />

recovered. The well block containing solidified<br />

material was then bisected vertically<br />

along the casting channel. Figure 5 shows<br />

one of the recovered backup well blocks.<br />

Starting the examination from the bottom<br />

of the casting channel, the first significant<br />

feature is the dome spanned cavity<br />

in the well block. This cavity contained<br />

flowable ladle well filler until the backup<br />

slide gate system was removed and the<br />

well block was excavated from the ladle<br />

bottom lining. The shown ladle well filler<br />

starts to form liquid phases above<br />

1,500°C, thus the flowable mass was<br />

exposed to lower temperatures. The<br />

dome above the cavity consists of a layer<br />

of sintered ladle well filler with a thickness<br />

of 3 – 6 cm. This layer formed during the<br />

cooling of the highly viscous silica melt<br />

phase covered in earlier publications.<br />

Overlying the sintered dome is a layer of<br />

steel pervaded by slag inclusions and<br />

shrinkage cavities. The boundary reactions<br />

between well block, steel and ladle<br />

well filler are subject of ongoing research.<br />

A comparison between the material cone<br />

after addition and the sintered dome<br />

shows a significant reduction in size, i.e.<br />

roughly a third of the added ladle well filler<br />

was eroded through physical mechanisms<br />

or thermochemical processes. The<br />

amount of erosion in the industrial trials<br />

varied over a wide range, determined by<br />

the duration of the secondary metallurgical<br />

treatment and the alloys in the produced<br />

steel quality. This dynamic process<br />

determines the progression of the surface<br />

of the dome into the casting channel. A<br />

more pronounced erosion of the ladle well<br />

filler and a further progression into the<br />

casting channel lead to a smaller diameter<br />

of the dome that can then withstand higher<br />

ferrostatic pressures consequently<br />

reducing the free opening rate. This is a<br />

possible explanation for the correlation of<br />

treatment duration and free opening rate<br />

which is described in numerous publications.<br />

Interaction between steel and ladle<br />

well filler<br />

The effect of the steel grade on the erosion<br />

of ladle well fillers was examined in<br />

laboratory tests conducted by Purmetall<br />

and Forschungsgemeinschaft Feuerfest<br />

with the goal to develop ladle well fillers<br />

especially suited for the conditions during<br />

the production of particular steel grades.<br />

To investigate the reactions between steel<br />

and ladle well filler a new crucible test, distinguished<br />

by the direct exposure of ladle<br />

well filler to liquid steel in an inert atmosphere<br />

at 1,600°C for a duration of two<br />

hours, was developed. Figure 6 shows an<br />

example of the two component crucible<br />

test setup.<br />

To recreate the specific working conditions,<br />

different ladle well fillers and steel<br />

grades were combined in these two com-<br />

Figure 5. Bisected<br />

well block from<br />

the industrial trial<br />

(Picture: Purmetall)<br />

Figure 3. Backup well block with added<br />

ladle well filler shortly before EAF tapping<br />

(Picture: Purmetall)<br />

Figure 4. Illustration of the backup well<br />

block after addition of 50kg of ladle well<br />

filler (Picture: Purmetall)<br />

<strong>STEEL</strong> + <strong>TECHNOLOGY</strong> 2 (<strong>2020</strong>) No. 1

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!