<strong>Public</strong> <strong>Information</strong> <strong>Booklet</strong><br />

Figure 19: Dredge material for northern site option<br />

Southern Site<br />

The wave cut platform at the southern location is narrower (approximately 1 kilometre)<br />

and deeper water is closer to shore. This will result in a significant reduction in both<br />

dredging volumes and potential blasting requirements.<br />

Preliminary estimates indicate a total dredging volume for a southern James Price Point<br />

site to be in the order <strong>of</strong> 6 to 8 million cubic metres or less than half the volume <strong>of</strong> the<br />

northern site. It is estimated about 10% <strong>of</strong> this material would need to be blasted to<br />

enable removal (pink area on Figure 20).<br />

A dredging program <strong>of</strong> 6 to 8 million cubic metres would typically be undertaken over a<br />

single dry season.<br />