Project management and the private finance initiative
Project management and the private finance initiative
Project management and the private finance initiative
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
The SPV is a limited company that is set up for <strong>the</strong> sole purpose<br />
of delivering <strong>the</strong> PFI project. It comprises parties from <strong>the</strong><br />
winning consortium, which will typically include a construction<br />
contractor, facility <strong>management</strong> provider, investors <strong>and</strong> o<strong>the</strong>r<br />
specialist contractors. The objectives of <strong>the</strong> SPV are to minimise<br />
<strong>the</strong> risks of delivering <strong>the</strong> project <strong>and</strong> to generate profits. In<br />
doing so it will pass down risks to sub-contractors, <strong>the</strong>reby<br />
limiting risk in <strong>the</strong> SPV. Limiting risk in <strong>the</strong> SPV is particularly<br />
important because consortia usually require access to third party<br />
funding, such as equity, bank loans or bonds. The objective of <strong>the</strong><br />
third party funders is to make a profit from <strong>the</strong>ir investment (Fox<br />
<strong>and</strong> Tott, 1999).<br />
Although many of <strong>the</strong> risks associated with PFI projects lie with<br />
<strong>the</strong> SPV, <strong>the</strong> awarding authority still has a critical role to play in<br />
managing <strong>the</strong> procurement process. Amongst o<strong>the</strong>r things, <strong>the</strong><br />
awarding authority is responsible for:<br />
• Establishing <strong>the</strong> business case;<br />
• Developing <strong>the</strong> public sector comparator 3 ;<br />
• Devising <strong>the</strong> output specification;<br />
• Inviting <strong>and</strong> evaluating bids; <strong>and</strong><br />
• Awarding <strong>and</strong> managing <strong>the</strong> contract (Treasury Taskforce, 1998).<br />
In doing so <strong>the</strong> awarding authority may call on <strong>the</strong> expertise of<br />
external consultants <strong>and</strong> advisors. This is particularly important<br />
in projects where awarding authorities have little or no<br />
experience of <strong>the</strong> PFI process.<br />
As of April 2003, 569 PFI contracts had been signed, 418 of which<br />
were already operational (OGC, 2003a). The combined capital<br />
value of <strong>the</strong>se contracts was £53 billion, although <strong>the</strong> value of<br />
individual projects ranged from under £1 million to over £1<br />
billion (OGC, 2003a). In <strong>the</strong> construction <strong>and</strong> property sector, <strong>the</strong><br />
scope of PFI has been wide-ranging, including roads, bridges,<br />
sewage treatment plants, waste incinerators, hospitals, schools,<br />
prisons <strong>and</strong> office accommodation.<br />
Research for Foundation for <strong>the</strong> Built Environment (Dixon et al,<br />
forthcoming) showed that in <strong>the</strong> early years of PFI (1992–1994)<br />
only 8 deals were signed, with a combined value of £630 million.<br />
PFI has grown in importance, however, with a peak in 2000,<br />
when 102 PFI contracts worth £4.3 billion were awarded. The<br />
research also showed that more than a third of PFI contracts<br />
awarded since 1992 were in <strong>the</strong> education or health sectors,<br />
comprising 19% of <strong>the</strong> total capital expenditure through PFI.<br />
A large number of PFI contracts have been awarded by <strong>the</strong><br />
Ministry of Defence (MoD) <strong>and</strong> <strong>the</strong> Home Office (mainly prisons)<br />
(Figure 2.2). Although fewer in number than health <strong>and</strong><br />
education projects, MoD <strong>and</strong> Home Office projects still comprise<br />
17% of total PFI capital expenditure since 1992. The most<br />
valuable PFI contracts have been awarded by <strong>the</strong> Department for<br />
Transport, its 31 PFI projects comprising 39% of total capital<br />
expenditure on PFI. In contrast, more than half of all o<strong>the</strong>r<br />
departments have procured less than 10 PFI projects,<br />
constituting just 12% of total PFI spending, <strong>and</strong> five of <strong>the</strong>se<br />
have procured only one project 4 .<br />
Despite <strong>the</strong> large number of projects procured to date, however,<br />
<strong>the</strong> effectiveness of PFI is still subject to considerable debate.<br />
A number of studies have suggested that PFI has delivered<br />
benefits over conventional public sector procurement (Arthur<br />
Andersen / Enterprise LSE, 2000; Ive et al., 2000; NAO, 2003a).<br />
For instance, a study of PFI projects by <strong>the</strong> National Audit Office<br />
revealed that only 22% of projects experienced increasing<br />
construction costs after <strong>the</strong> contract had been awarded (NAO,<br />
2003a). Ive et al. (2000) found average total cost savings of<br />
between 5% <strong>and</strong> 10% compared with conventionally procured<br />
projects, <strong>and</strong> Arthur Anderson <strong>and</strong> Enterprise LSE (2000)<br />
identified average cost savings of 17%.<br />
Never<strong>the</strong>less, <strong>the</strong> use of PFI has not been without problems (Audit<br />
Commission, 2003; NAO, 2003b; Ive et al., 2000). A survey of PFI<br />
schools by <strong>the</strong> Audit Commission (2003) suggested that <strong>the</strong> quality<br />
of PFI schools was lower than those that had been procured<br />
conventionally. Similarly, a National Audit Office study of PFI<br />
prisons concluded that <strong>the</strong> operational performance of projects,<br />
as measured against <strong>the</strong> terms of contracts, had been mixed<br />
(NAO, 2003b). PFI has also been criticised for its high transaction<br />
costs, reflecting <strong>the</strong> complexity of <strong>the</strong> procurement process. For<br />
example, legal <strong>and</strong> advisory fees have, on average, been 10% to<br />
20% higher than under conventional procurement (Ive et al., 2000).<br />
3 The public sector comparator (PSC) is <strong>the</strong> benchmark project against which <strong>the</strong> PFI option <strong>and</strong> <strong>private</strong> sector bids are evaluated (Treasury Taskforce, 1998).<br />
4 There have also been a number of large PFI IT projects, which have produced mixed results. Recent high profile cases which have run into problems include new IT systems for <strong>the</strong> child<br />
support agency <strong>and</strong> <strong>the</strong> criminal records bureau (Denny, 2003). The Government has decided to restrict PFI to large projects because in <strong>the</strong>ir view (HM Treasury, 2003), high legal <strong>and</strong><br />
financial costs make projects less than £20m poor value. A more detailed review <strong>and</strong> analysis of such projects is expected from <strong>the</strong> Treasury in autumn 2003.<br />
<strong>Project</strong> <strong>management</strong> <strong>and</strong> <strong>the</strong> <strong>private</strong> <strong>finance</strong> <strong>initiative</strong> chapter two Managing <strong>the</strong> <strong>private</strong> <strong>finance</strong> <strong>initiative</strong><br />
4