PROJECT PROJECT MANAGEMENT<br />
MANAGEMENT<br />
and engineering, procurement & construction<br />
management costs, (xix) first fills & reagents, (xx)<br />
technical investigations, (xxi) taxes, duties and<br />
surcharges, (xxii) fees and royalties, (xxiii) land<br />
acquisition, (xxiv) owner pre-production and other<br />
costs, (xxv) escalation, (xxvi) foreign currency, (xxvii)<br />
allowances, (xxviii) accuracy assessment, (xxix)<br />
contingency calculation, (xxx) estimate summary,<br />
(xxxi) cash flow forecast, (xxxii) exclusions, (xxxiii)<br />
assumptions, and (xxxiv) comparison with earlier<br />
estimates about similar projects.<br />
As the project estimate is being developed, all<br />
potential cost risks should be recorded. During the<br />
preparation of a project estimate, the estimator may<br />
encounter a number of items that could present<br />
potential cost risk to the project. The list of cost risks<br />
may include such things as unquoted equipment,<br />
unidentified engineering or construction resources,<br />
potential labor issues (such as looming strikes or<br />
shortage of qualified labor), unknown site conditions,<br />
etc. All of these risks should be clearly identified<br />
within the basis of estimate to ensure that’all project<br />
team members are made aware of their existence.<br />
Documentation is a key element in good estimating<br />
practice. The estimate file should be a well-organized,<br />
easy to follow history from the first estimate at the<br />
beginning of the planning phase through preparation<br />
of the final estimate. The basis of estimate document<br />
contains recommended organization, topics and<br />
format. Each estimate should track changes from the<br />
previous estimate, updating the scope, assumptions,<br />
quantity and price calculations, and risks from the<br />
previous estimate. At each update the differences<br />
between the previous estimate and the current<br />
estimate should be highlighted. <strong>This</strong> contributes to<br />
transparency and accountability in estimating and<br />
promotes the consistency between estimates.<br />
Several techniques can be employed to ensure<br />
good documentation. It is recommended that<br />
estimating be specifically scheduled in the project<br />
management plan for each phase of the project. <strong>This</strong><br />
ensures that adequate time and resources are allotted<br />
for performing the estimate. A specific schedule<br />
should be developed for each estimate. As part of the<br />
estimate review process, someone external to the<br />
project team should perform a review of the estimate<br />
file. <strong>This</strong> external review will help ensure that the<br />
estimator has clearly recorded the assumptions and<br />
decisions made in the estimating process.<br />
A well prepared basis of estimate will (i) document<br />
the overall project scope, (ii) document the items that<br />
are excluded from the project scope, (iii) document<br />
the key project assumptions, (iv) communicate the<br />
estimator’s knowledge of the project by demonstrating<br />
an understanding of scope and schedule as it<br />
relates to cost, (v) alert the project team to potential<br />
cost risks and opportunities, (vi) provide a record of<br />
key communications made during estimate<br />
preparation, (vii) provide a record of all documents<br />
used to prepare the estimate, (viii) act as a source of<br />
support during dispute resolutions and for bid<br />
analysis, (ix) establish the initial baseline for scope,<br />
quantities and cost for use in cost trend evaluation<br />
throughout the project, (x) provide the historical<br />
relationships between estimates throughout the<br />
project lifecycle, (xi) facilitate the review and<br />
validation of the cost estimate.<br />
The following sections should be included in the<br />
basis of estimate document :<br />
i. Project objective and overview: <strong>This</strong> initial<br />
section provides a brief and concise description of the<br />
project. We may include all the following project<br />
information within that description - the purpose, the<br />
physical location, the position of the project within<br />
the organizational structure, the sponsors of the<br />
project, and the expected start and finish dates.<br />
ii. Project scope description : <strong>This</strong> section should<br />
be organized to correspond with the project’s work<br />
breakdown structure (WBS). A brief description of<br />
the scope of work should be provided for the major<br />
segments of the project. We should select the major<br />
WBS items that will apply to the estimate to be<br />
prepared and list for each the WBS number, task/<br />
item title, period of performance, and detailed<br />
description including related trades.<br />
iii. Estimate base sources : The base sources i.e.<br />
the design basis, planning basis, and cost basis are<br />
the referenced documentation that forms the<br />
foundation for the estimate. For short items, we may<br />
copy the information to the BOE. For larger items,<br />
we should provide references to documents. The<br />
listing against each item may include its name, brief<br />
description, and document number. We should also<br />
mention the primary estimating methodology that will<br />
be used to prepare the cost estimate.<br />
iv. Design basis : In this section, the estimator will<br />
identify the types and status of engineering and design<br />
deliverables that were provided to prepare the<br />
estimate including any design basis assumptions. We<br />
should record the items that will be used to form the<br />
estimate e.g. drawings, requirements, operational<br />
concept documents, specifications, equipment and<br />
tools, and the deliverables.<br />
v. Planning basis : <strong>This</strong> section documents the<br />
project management, engineering, design, procurement,<br />
fabrication, and construction approaches to the<br />
The Management Accountant |September 2011 767