40 Installation Qualification (IQ)<br />
Installation Qualification (IQ)<br />
Installation report Certification on the functionality of the device. During installation<br />
of the device, an installation report (IQ document) is created<br />
upon request in coordination with the technical support of<br />
the manufacturer.<br />
This installation report needs to be completed in full and signed<br />
by both parties. It serves as proof of the properly executed<br />
installation and the functionality of the device.<br />
Operation Qualification (OQ)<br />
Extensive<br />
functionality test<br />
Extensive test of the detector's functionality. A successfully executed<br />
OQ ensures that the detector functions properly.<br />
Test Intervals<br />
Run the device test at the following time intervals:<br />
Average useful life Device test<br />
1 to 5 days/week: Every 6<br />
months<br />
More than 5 days/week or 24 hours/day: Every 3<br />
months<br />
Operation with buffer solutions or other salt<br />
solutions:<br />
Execution<br />
Every 3<br />
months<br />
The execution is done either by the manufacturer's technical service<br />
or by a technical service authorized by the manufacturer.<br />
Note The OQ documentation required for executing the OQ is with<br />
costs (once) and can be ordered separately from the manufacturer.