MOD. 2HYD<br />

GUIDELINES FOR THE INSTALLATION ENGINEER<br />

CONTROLS TO BE CARRIED OUT AFTER INSTALLATION<br />

LIFT Type................................................................................... Serial number.......................................................<br />

YES NO NOTE:<br />

1. CHECK THAT INSTALLATION AND TIGHTNESS OF FLOOR ANCHORS ARE CORRECT<br />

2. CHECK THAT ELECTRICAL CONNECTION IS IN COMPLIANCE TO THE NORMS<br />

3. CHECK THAT THE PNEUMATIC SUPPLY IS CORRECT (IF INSTALLED)<br />

4. CHECK THAT THE LIFT OPERATION IS CORRECT ACCORDING TO USER MANUAL<br />

5. CHECK THE CORRECT FUNCTION OF THE ELECTRICAL SAFETY DEVICES<br />

6. CHECK THE EMERGENCY BUTTON OPERATION<br />

7. CHECK THE CORRECT INSERTING OF THE MECHANICAL SAFETY DEVICES<br />

8. CHECK THE CORRECT INSERTING OF THE ARMS LOCKING DEVICES<br />

9. CHECK THE CORRECT ASSEMBLING OF THE ANTI-TOE TRAPPING DEVICES<br />

10. CHECK THE PERFECT SEALING OF THE HYDRAULIC SYSTEM<br />

11. CHECK THE OIL LEVEL<br />

12. CHECK THE EMERGENCY LOWERING OPERATION<br />

13. CHECK THE APPLICATION OF THE WARNING LABELS, AS PER LAYOUT<br />

14. CHECK THE CORRECT LUBRICATION OF GUIDES<br />

15. LIFT TESTING WITH MAXIMUM LOAD<br />

16. CHECK DOCUMENTATION (user manual & declaration of conformity)<br />

17. TRAINING OF PERSONNEL QUALIFIED TO USE THE LIFT<br />

NOTE:<br />

Date: User: Installation engineer:<br />

_____/______/_____ Stamp and Signature Stamp and Signature<br />