10.2.2 Independent Monitoring Panel<br />
Cowal <strong>Gold</strong> Project – Cyanide Management Plan<br />
The Independent Monitoring Panel will, amongst other things, review the Independent Audit required by<br />
Consent Condition 8.8(a). In accordance with Consent Condition 8.8(b):<br />
(i) The Applicant shall at its own cost establish an Independent Monitoring Panel prior to<br />
commencement of construction. The Applicant shall contribute $30,000 per annum for the<br />
functioning of the Panel, unless otherwise agreed by the Director-General. The annual payment<br />
shall be indexed according to the Consumer Price Index (CPI) at the time of payment. The first<br />
payment shall be paid by the date of commencement of construction and annually thereafter.<br />
Selection of the Panel representatives shall be agreed by the Director-General in consultation with<br />
relevant government agencies and the CEMCC. The Panel shall at least comprise two duly qualified<br />
independent environmental scientists and a representative of the Director-General.<br />
(ii) The panel shall:<br />
a. provide an overview of the independent audits required by condition 8.9 above;<br />
b. regularly review all environmental monitoring procedures undertaken by the Applicant, and<br />
monitoring results; and<br />
c. provide an Annual State of the Environment Report for Lake Cowal with particular reference<br />
to the on-going interaction between the mine and the Lake and any requirements of the<br />
Director-General. The first report shall be prepared one year after commencement of<br />
construction. The report shall be prepared annually thereafter unless otherwise directed by<br />
the Director-General. Copies of the report shall be provided to those parties which receive<br />
the AEMR (condition 9.2) and shall be made publicly available at Bland Shire Council within<br />
two weeks of the report’s completion.<br />
10.3 INTERNAL REVIEW<br />
In accordance with Consent Condition 3.2 the CMP will be revised/updated at least every five years, or<br />
as otherwise directed by the Director-General for Planning, in consultation with the relevant<br />
government authorities.<br />
The cyanide monitoring programme will be revised/updated annually, unless otherwise directed by the<br />
Director-General, to reflect changing environmental requirements, significant changes in technology/<br />
operational practices and results from the monitoring conducted in accordance with Consent<br />
Condition 8. The changes will be made and approved through the AEMR process.<br />
11 REFERENCES<br />
American Public Health Association (APHA) (1998). Standard Methods for the Examination of Water<br />
and Wastewater, 20th Edition, 4500-CN. American Public Health Association, Washington.<br />
Australian Heritage Commission (1992). Register of the National Estate. Detailed Place Report for<br />
Lake Cowal. Australian Heritage Commission, Canberra.<br />
<strong>Barrick</strong> Australia Limited (2003a). Cowal <strong>Gold</strong> Project Hazardous Waste and Chemical Management<br />
Plan.<br />
<strong>Barrick</strong> Australia Limited (2003b). Cowal <strong>Gold</strong> Project Site Water Management Plan.<br />
HAL-02-07/1/25/CMP-01-Q.DOC 31 BARRICK