Chapter<br />
3<br />
10<br />
Invitation to tender<br />
3.2.5 Window fittings (hardware) ➔<br />
The window fittings have to meet the requirements of DIN EN 13126. They<br />
have to be manufactured and protected against corrosion according to the<br />
expected strains. The informations of the manufacturer of the fittings have<br />
to be taken into consideration.<br />
Accessory parts as e.g. limiters are to be cited in individual position descriptions.<br />
The operating height of the handle has to be determined and<br />
the handles are to be fixed (if appropriate) in each room at the same<br />
height. The window handles have to be in the same colour, surface etc. as<br />
indicated.<br />
3.2.6 Glazing bars ➔<br />
Beside glazing bars dividing the glazed profiles with or without a distance<br />
piece in the space between the panes (sbp/SZR) as well as systems inserted<br />
into this space can be used. In case of glazing bars in the sbp/SZR it is possible<br />
that they can contact the glass surface as a result of the opening and<br />
closing of the window or of other mechanical influences. This may cause a<br />
rattling noise.<br />
3.3 3.3 General technical requirements<br />
3.3.1 Dimensions of the windows ➔<br />
Before the fabrication starts, the consignee is responsible for making the necessary<br />
final measurements (the reference marker has to be made by the carcass<br />
manufacturer). If the carcass tolerances are over the guidelines of DIN 18202<br />
the client has to be informed verbally and in writing without delay.<br />
We emphasise particularly that, as a basic principle, according to § 4 No.<br />
3 VOB/B, the consignee has to complete obligation for checking and indication.<br />
3.3.2 Working at height ➔<br />
When working at height is needed, scaffolding may be required and the director<br />
of works needs to be contacted in good time. Working practises should<br />
comply with the employer’s insurance requirements and, if necessary, any site<br />
regulations.<br />
All scaffolding necessary for inside and all movable platforms up to 2 m are<br />
to be made available by the consignee. The resulting costs are to be included<br />
in the calculation of the flat prices.<br />
If the consignee has to make scaffolding available, the regulation on<br />
which the corresponding offer is made is DIN 18451. For that reason this<br />
specification contains a service item.<br />
3.3.3 Waste disposal ➔<br />
<strong>Windows</strong> and other building components which have to be removed in conjunction<br />
with the specifications in the invitation to tender, as well as other<br />
waste, are to be disposed of according to the Environmental Protection<br />
regulations. Note any special local regulations!<br />
If the waste contains harmful substances the client has to be informed<br />
verbally and in writing without delay.<br />
Operating height (from FFL):<br />
From to mm<br />
Design of window handles:<br />
No glazing bars<br />
Glass dividing<br />
Affixed with distance piece<br />
Affixed without distance piece<br />
Glazing bars in the space<br />
between panes<br />
Sightline:<br />
Measurements<br />
Complete<br />
Incomplete<br />
RAL-GÜTEGEMEINSCHAFT KUNSTSTOFF-FENSTERSYSTEME<br />
mm<br />
Scaffold provided by the customer<br />
Scaffold to be provided<br />
Components which have to be removed<br />
Number of windows<br />
Number of doors<br />
Other