Fig. 2: Diagramfor the determination<br />
of the ìnal measurements<br />
Exactly measured is<br />
half installed<br />
The limit deviations of DIN 18202, table 1, apply to wall open-<br />
ings. They are in extracts given in the following chart 1. A<br />
professional installation is only possible if a reveal formation<br />
according to line 6 is given. It must be ensured that the win-<br />
dows can be installed horizontally, vertically and flushly.<br />
The accuracy of the spirit levels is to be taken into consider-<br />
ation. For an element of up to 3,00 m in length the maxi-<br />
mum permissible tolerance for variations of the vertical and<br />
Final measurements and determination of the real building situation<br />
horizontal lines are 1,5 mm/m, up to a maximum of 3 mm.<br />
If, due to the exceeding of tolerance margins or variations<br />
to the given building situation, changing or additional<br />
measures are necessary, these have to be stipulated be-<br />
fore the start of installation.<br />
Column 1 2 3<br />
Nominal dimension up to 3 (m) more than 3-6 (m)<br />
Line Reference Limit deviations (mm)<br />
5 Openings for e.g. windows, doors, installation elements ± 12 ± 16<br />
6 Openings like above-mentioned but with surface-finished reveals ± 10 ± 12<br />
“Surface-finished reveals" also means that there are no joints<br />
with bricks, clinker bricks etc.<br />
OFF = upper surface floor<br />
ORF = upper surface raw floor<br />
Spirit level<br />
Parapet height<br />
Chart 1: Limit deviations for building dimensions according to DIN 18202 (extract)<br />