Planning of the installation<br />
5. Planning of the installation<br />
The planning of the installation can start after the final<br />
measurements. Therefore the following points are to be<br />
considered:<br />
● To simplify the operation, the areas of responsibilities are<br />
to be precisely defined and clearly named. (e.g. is the in-<br />
stallation company responsible for all sealings? Is clean-<br />
ing necessary? etc.)<br />
● In general, the extra work and specific performances de-<br />
scribed in the offer shall be controlled during the final<br />
measurements.<br />
● The condition of the window recess under the window,<br />
which is to be removed, is important for the choice of the<br />
right fixing agent, especially in case of reconstruction of<br />
old buildings.<br />
● It is also to be clarified if the removal of the old windows<br />
and their disposal is to be calculated as extra work or spe-<br />
cific performance.<br />
5.1 Organisational planning<br />
■ Points of intersection / area of responsibility<br />
- steel trowel finish of the window respond in the case of<br />
new buildings<br />
- sealing of the windows<br />
- plastering of the inner recess<br />
■ Control of the procedure documentation<br />
- finale measurements and position plans<br />
- technical drawings or isothermal representations<br />
- work instructions<br />
- list of material<br />
■ Removal of the old window in case of renovation<br />
- schedule<br />
- announcement of the works<br />
- disposal or recycling of the old windows<br />
■ Installation of the new windows<br />
- time planning<br />
- cleaning, remove protective foil<br />
- make the hand-over or at least arrange it<br />
■ General details<br />
- training of the personnel<br />
- in case of window walls use only the permitted assem-<br />
bling auxiliaries<br />
- avoid soiling, especially in case of coloured profiles<br />
5.2 Installation planning<br />
If not emphatically required, all elements are to be installed<br />
vertically, horizontally and flushly. If the exact position of the<br />
windows and doors in the building is not exactly defined, it has<br />
to be stipulated in writing with the customer or with the planner.<br />
5.2.1 Fastening in the building<br />
The fastening of the windows and doors in the building is the<br />
basis of the installation. All forces affecting the window ac-<br />
cording to plan have to be transferred into the building. This<br />
must be done before the fastening with the necessary security<br />
and with regard to the movements occuring in the interface.<br />
5.2.2 General principles<br />
According to the German Building Regulations of the Land the<br />
windows have to be anchored in such a way that neither life and<br />
health of people are in danger nor public safety compromised.<br />