CAC Item No. 23<br />

Name <strong>of</strong> the industry : M/s. B.S. ISPAT LTD.,(sponge Iron Plant)<br />

Vill-Salori Yensa,Tal-Warora, Dist.- Chandrapur.<br />

HOD Remarks :<br />

1. M/s B.S.Ispat Ltd,Salori Yensa, Ta warora, dist Chandrapur, is engaged in<br />

manufacturing <strong>of</strong> sponge iron.<br />

2. Earlier application for first consent <strong>to</strong> operate was refused by the Head<br />

<strong>of</strong>fice vide letter dated 01/02/2012 due <strong>to</strong> non compliance <strong>of</strong> consent <strong>to</strong><br />

establish conditions and accordingly Regional Office vide letter dated<br />

29/02/2012 has issued directions not <strong>to</strong> operate industry unless obtaining<br />

valid consent <strong>to</strong> operate from the Board.<br />

3. Now, the said industry has made fresh application for first consent <strong>to</strong><br />

operate for sponge iron plant for production <strong>of</strong> 60,000 TPA (Phase-I).<br />

4. Capital Investment <strong>of</strong> the Sponge iron plant is Rs. 65.24 crore. Total Capital<br />

Investment <strong>of</strong> integrated project including sponge iron plant as per the<br />

consent <strong>to</strong> establish granted earlier is Rs.158.5/- crore.<br />

5. <strong>Consent</strong> Fees <strong>of</strong> Rs.2,00,000/- had <strong>be</strong>en <strong>submitted</strong> with earlier consent<br />

application which was refused. Hence we may forfeit one term consent fees<br />

<strong>of</strong> Rs.1,00,000/- and consider Rs.1,00,000/- for this consent <strong>to</strong> operate.<br />

6. Obtained Environmental Clearance from the MoEF, GOI, vide letter dated 5th<br />

May 2009 for sponge iron unit with captive power plant , for sponge iron <strong>of</strong><br />

production <strong>of</strong> 64000 TPA & further obtained EC vide letter dated 23 rd<br />

Novem<strong>be</strong>r 2010 for production <strong>of</strong> sponge iron <strong>of</strong> 64000 TPA <strong>to</strong> 184000 TPA,<br />

copy is enclosed.<br />

Now unit has installed necessary pollution control system including<br />

installation <strong>of</strong> CAAQMS & Opacity meter. The compliance is <strong>submitted</strong> by RO<br />

/SRO. We may grant consent <strong>to</strong> operate up <strong>to</strong> 30.4.2013 with operational bank<br />

guarantee <strong>of</strong> Rs.5/- Lakhs <strong>to</strong>wards pollution control system.