6.4 Equipment capacity<br />

- 27 -<br />

6.4.1 Number of controlled stations<br />

The number of controlled stations to be commissioned initially is indicated<br />

in the particular specification referred to in clauses 10 beroof. However, the SCADA<br />

equipment at RCC shall be designed and engineered to control about <strong>12</strong>0% of the number<br />

of stations to be commissioned initially. The extra capacity shall be available for<br />

expanding the system in future. It shall be possible to realize the extra capacity simply by<br />

adding the required functional modules in the spare sub racks of the mimic driver and<br />

incorporating. Necessary changes in the software and MDB at RCC, without affecting the<br />

existing system either physically or operationally.<br />

6.4.2 Number of telecommands, telesignals and telemetered parameters<br />

(measurands)<br />

6.4.2.1 The SCADA equipment shall be designed for the following capacity of<br />

telecommands, telesignals and telemetered parameters for a typical TSS, SSP, SP and<br />

ATP of a double line section.<br />

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -<br />

S. No. Controlled Telecommands Telesignals Measurands<br />

station<br />

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -<br />

1 TSS 24* 88 8<br />

2 SP 8* 20 4<br />

3 SSP 8 <strong>12</strong> -<br />

4 ATP - 8 -<br />

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -<br />

* No of telecommands for faultlocator is not included, it is to be added where applicable.<br />

6.4.2.2 The above figures may vary depending on the layout of TSS, SP, SSP and<br />

ATP in a particular section, which could have three or more tracks, the details of which<br />

will be contained in the particular specification referred to in clause-10 hereof.<br />

6.4.2.3 The number of parameters to be commissioned initially may be less than the<br />

above figures and the balance designed capacity shall be available for future use. A<br />

typical requirement of telecommands, telesignals and telemetered parameters on a double<br />

line section is at Annexure-I.