2. Site Information and Planning Assessment<br />

2.1 Site and Environment<br />

The plan below illustrates the area of land ownership of the Farm, consisting of 37 fields with a combined<br />

site area of 258.58 hectares.<br />

Figure 2: Site Location Plan<br />

Land Ownership Boundaries supplied by ILI<br />

The surrounding land use is agricultural, with plantation forestry approximately 881m to the Southeast of<br />

the proposed turbine location. Caplaw Dam Reservoir is located approximately 786m the East from the<br />

proposed turbine location, with Old Patrick Water located approximately 831m to the Southeast were it<br />

feeds the Caplaw Dam Reservoir. There is also a small drainage channel to the Northwest. To the<br />

Northeast is a large electricity substation approximately 2.5km away, with seven high voltage lines and<br />

associated high rise pylons heading to the South and Southeast, and two further high voltage lines<br />

heading to the Northwest. Further to the Northeast, is Gleniffer Braes Country Park. There are numerous<br />

telecommunications masts in the area.<br />

Waterman Group, Renewable Energy, 2/4 Canning Street Lane, Edinburgh, EH3 8ER T:0131 221 7020<br />

3<br />

K:\Projects\CIV12920_ILI Windfarms_Batch 7\CIV12920_XXX_Hartfield<br />

Farm\Documents\Reports\CIV12920_1202xx_Hartfield_<strong>Supporting</strong> Turbine Assessment_225kW.docx

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!