- Page 5 and 6:
1 Executive summary The main goal o
- Page 7 and 8:
4 Sessions 4.1 General indications
- Page 9 and 10:
4.2.2 Acoustic sensors 4.2.2.1 Intr
- Page 11 and 12:
In the marine environment a diversi
- Page 13 and 14:
4.3.1.3 Debriefing - A document was
- Page 15 and 16:
defined by ESONET deliverables D11
- Page 17 and 18:
The generic sensor should be availa
- Page 19 and 20:
The oxygen sensor in the generic sp
- Page 21 and 22:
Common topics on time series analys
- Page 23 and 24:
Ecological communities Author: H. R
- Page 25 and 26:
Pan & tilt system, to find the righ
- Page 27 and 28:
References : http://www.listentothe
- Page 29 and 30:
Zaugg, S., van der Schaar, M., Hou
- Page 31 and 32:
e: connection e represents the conn
- Page 33 and 34:
Case Study In order to test the Ref
- Page 35 and 36:
operate it in a safe and productive
- Page 37 and 38:
White Paper for the Panel 3-3 - 20
- Page 39 and 40:
springs for release has shown its p
- Page 41 and 42:
Cathodic protection, including the
- Page 43 and 44:
Thursday 8 October Time Topic 09:00
- Page 45 and 46:
Friday 9 October Time Topic 08:15 S
- Page 47 and 48:
Generic session scheme Presentation
- Page 49 and 50:
o Existing or newly developed quali
- Page 51 and 52:
Working group G3 - Standardisation
- Page 53 and 54:
Objectives: The first meeting of th
- Page 55 and 56:
Firstname Lastname Institution Coun
- Page 57 and 58:
Annex C Slides from Anders Tendberg
- Page 59 and 60:
Criteria for Observatory Sensors Fi
- Page 61 and 62:
Possible sensor technology for obse
- Page 63 and 64:
http://www.act-us.info/ EURO ACT, l
- Page 65 and 66:
Calibration methods Temp Pr Current
- Page 67 and 68:
Which problems remain to be solved
- Page 69 and 70:
Tests : • Fluorescence sensors :
- Page 71 and 72:
Local Protection by electrochlorina
- Page 73 and 74:
WG 1 GENERIC INSTRUMENTATION PANEL
- Page 75 and 76:
Physical and Technological constrai
- Page 77 and 78: Annex D EARTH SEA SCIENCE IN KM3Net
- Page 79 and 80: I - Manage data from the above. (Sp
- Page 81 and 82: Figure 2: Secondary junction box of
- Page 83 and 84: Docking unit is also the structural
- Page 85 and 86: Infrastructure / Standalone observa
- Page 87 and 88: Infrastructure / Standalone observa
- Page 89 and 90: Annex F1: processing of ELISA data
- Page 91 and 92: Figure 2: currents measured around
- Page 93 and 94: depth (m) Due to inertial currents
- Page 95 and 96: Figure 6: Rebuilt Time series of sa
- Page 97 and 98: ANNEXE F2 - M. FAUZI's presentation
- Page 99 and 100: 40 km submarine cable -2475m depth
- Page 101 and 102: CTD ADCP Interdisciplinary Instrume
- Page 103 and 104: Deliverable #50 -
- Page 105 and 106: Shore Station : M. Pacha 40km Elect
- Page 107 and 108: Antares Database and Web site proje
- Page 109 and 110: Deliverables / Pla
- Page 111 and 112: Istituto Nazionale di Geofisica e V
- Page 113 and 114: Just in time data conversion Web GU
- Page 115 and 116: Deliverable #50 -
- Page 117 and 118: Let’s see it live SeaFloor test s
- Page 119 and 120: Ecological Communities •Species c
- Page 121 and 122: Spatio-Temporal Correlations • Ti
- Page 123 and 124: Deliverable #50 -
- Page 125 and 126: E. minutissima Ec. rostrata Density
- Page 127: 10-12 months for the RAD (r = 0.38;
- Page 131 and 132: Total density (TA D)(ind. grab -1 )
- Page 133 and 134: El Niño Southern Oscillation, Nort
- Page 135 and 136: Fishery Sciences and Technology Dep
- Page 137 and 138: Fishery Sciences and Technology Dep
- Page 139 and 140: Fishery Sciences and Technology Dep
- Page 141 and 142: Fishery Sciences and Technology Dep
- Page 143 and 144: ANNEX F6 - DEBRIEFING : Del
- Page 145 and 146: Introduction • From the first Bes
- Page 147 and 148: Time-Series Analysis Considerations
- Page 149 and 150: • CTD F, Bio, etc…. Time series
- Page 151 and 152: Deliverable #50 -
- Page 153 and 154: CTD Some examples of time series
- Page 155 and 156: Development of an Automated Protoco