5.3 Geo-referencing<br />

In order to meet project requirements that the survey be geo-referenced, a five station GNSS<br />

session was observed using one dual frequency <strong>and</strong> four single frequency receivers. The 7 hour<br />

data file from the dual frequency observation was submitted to the Precise Point Positioning<br />

Service (PPP) provided by Geodetic <strong>Survey</strong>s <strong>of</strong> Canada for processing. The absolute accuracy<br />

for the results was 0.02m at the 95% confidence level. Two new concrete pins (Stations 1200 <strong>and</strong><br />

1202) were established in the general project area, <strong>and</strong> temporary nails were set at the Road<br />

Allowance between Lots 13 <strong>and</strong> 14 <strong>and</strong> also at Baseline Road. Another nail was set at the<br />

Concession 4 road, strictly to provide better geometric structure to the network. A four hour<br />

GPS session was observed in the field, <strong>and</strong> downloaded <strong>and</strong> processed using Spectrum v4.2.2<br />

s<strong>of</strong>tware. For preliminary processing we used the value for Station 1002 as measured relative to<br />

Station 2 from Plan 51R-34310 (As determined by RTK measurements - see para. 5.4) as a fixed<br />

base point. The results <strong>of</strong> this survey were excellent, with worst-case 95% confidence error<br />

ellipses <strong>of</strong> 0.006m for the stations. Co-ordinates are for UTM Zone 17 (NAD83-CSRS).<br />

Elevations are also based on the PPP observation <strong>and</strong> processing <strong>and</strong> are orthometric, referred<br />

to the CGVD28 datum.<br />

During our time on site during August 2013, a second 6.5 hour dual frequency GPS observation<br />

was made over Station 1202 to verify our results. After processing by PPP, the results (with<br />

estimated 0.025m accuracy at the 95% confidence level) agreed with the previous value within<br />

0.02m.<br />

Page 24 <strong>of</strong> 66