5.4 <strong>Field</strong> Procedures<br />

All field measurements were made using a Sokkia ISX2700 Real Time Kinematic (RTK) GPS<br />

system. For the first day <strong>of</strong> field operations the base unit was set in a clear area close to the area<br />

being worked in <strong>and</strong> the system was ‘localized’ (or referenced) to Station 2 on Plan 51R-34310,<br />

assuming that this would put us in a reliable UTM co-ordinate system, since we did not have a<br />

point with known co-ordinates to reference to. On the second day we again localized to Station<br />

2, so that all points were in a common co-ordinate system. Ties were also made to some remote<br />

survey monuments in Lots 9 <strong>and</strong> 14, <strong>and</strong> for these points, the RTK system was localized to GPS<br />

Stations 1203 <strong>and</strong> 1201, respectively.<br />

Once the final GPS processing relative to the PPP value for Station 1200 had been completed,<br />

the entire field co-ordinate file underwent a co-ordinate transformation to make the file 3-<br />

dimensionally correct. It turns out that our final co-ordinate values do not compare favourably<br />

with those by Plan 51R-34310 at all, so all co-ordinates needed to undergo a 3-dimensional shift<br />

to be in an accurate <strong>and</strong> reliable system. As a check on our work I compared our measured value<br />

for the Lambden control point at Jackson Point with our own. We agree vertically within 0.04m<br />

with the Lambden value, but differ by several metres with his horizontal values. Since the<br />

Lambden work was done in 2001, I suspect that it is in NAD83 (original). The PPP Observation<br />

we observed on our return trip verifies our values. As a further check, <strong>and</strong> to underst<strong>and</strong> the<br />

impact <strong>of</strong> our work on the lots in Reg’d. Plan 779, we also measured to four points from the<br />

O.L.S. Stewart Boundaries Act application on Lots 42, 43, 44 <strong>and</strong> 45. Again we agreed within<br />

0.02m with the co-ordinate values shown on that plan.<br />

All measurements to survey bars consisted <strong>of</strong> a first sequence <strong>of</strong> 10 ties which were averaged.<br />

Following this tie, a loss <strong>of</strong> satellite lock was forced, after which the system was allowed to reacquire<br />

satellite lock <strong>and</strong> an independent check measurement was obtained for verification <strong>of</strong> the<br />

initial averaged value. In the event that the comparison is not satisfactory, the process is<br />

repeated, until we are confident that the repetition tie <strong>and</strong> check tie are compatible, <strong>and</strong> that no<br />

corruption <strong>of</strong> the GPS signal is taking place.<br />