2.4.2 Pinal County Transportation Plan Final Report, 2000 Update, Lima & Associates,<br />
September 2000<br />
This <strong>study</strong> is a long-range transportation plan for <strong>road</strong>s of regional significance in Pinal County,<br />
including Interstates 8 and 10, state routes, and major county <strong>road</strong>s. This project is relevant to<br />
the SR <strong>77</strong> <strong>corridor</strong> <strong>study</strong> because it contains access management recommendations by <strong>road</strong>way<br />
classification, contains <strong>road</strong>way classifications and recommends future projects. The <strong>study</strong><br />
involved analyzing existing socioeconomic and transportation conditions, developing and<br />
analyzing future conditions to determine deficiencies and developing a program to identify<br />
transportation projects to correct deficiencies. SR <strong>77</strong> and SR 79 are functionally classified as<br />
minor arterials in the existing (Year 1999) conditions section of the plan. Other routes that are in<br />
the project <strong>corridor</strong> are classified as follows:<br />
• Saddlebrooke Boulevard – minor collector<br />
• Biosphere Road – minor collector<br />
• American Avenue – major collector<br />
The Transportation Plan for Pinal County consists of a Transit Element and a Street Element.<br />
The Transit Element recommends establishment of a task force to develop and maintain<br />
partnerships among human service providers, major employers, and municipalities. The task<br />
force would begin identifying the most appropriate institutional arrangement for the delivery of<br />
transit services. The Street Element includes a future functional classification system and<br />
recommended cross sections for each classification. SR <strong>77</strong> in Pinal County is classified as minor<br />
arterial in the future plan between SR 79 and Winkelman. SR <strong>77</strong> is classified as principal arterial<br />
between the Pinal County southern boundary and SR 79. SR 79 is classified as a principal<br />
arterial its entire length within Pinal County. The plan includes recommended cross sections<br />
associated with each <strong>road</strong>way classifications. Access management recommendations are<br />
provided in the <strong>report</strong>, including driveway spacing, driveway corner clearance, and driveway<br />
location restrictions. The <strong>report</strong> also presented level of service estimates assuming three future<br />
population levels. There is one future project within the <strong>study</strong> area, which is to widen SR 79,<br />
from Oracle Junction to SR 287, to four lanes.<br />
2.4.3 Southern Pinal County Regional Transportation Plan, Entranco, Inc., April 2003<br />
This transportation plan was developed for Southern Pinal County, which includes the area south<br />
of Coolidge, Florence and Kelvin, and east of Casa Grande and Chuichu. Most of the land in<br />
this area is undeveloped. The goal of the project was to determine the mitigation measures<br />
necessary to ensure quality transportation as the region develops. The results of the <strong>study</strong><br />
determined that nearly 18,000 new homes would likely be constructed in the Pinal County<br />
region, increasing population by nearly 55,000 persons. Adding to this residential development<br />
are more than 13,000 jobs. New development throughout the county could increase traffic by<br />
more than 60 percent over the next 20 years. One improvement was recommended within the<br />
<strong>study</strong> area, which is to widen SR <strong>77</strong>, from SR 79 to Reddington Road from two to four lanes.<br />
Traffic volumes are anticipated to increase from 12,500 vpd to 16,400 vpd.<br />
SR <strong>77</strong>/Oracle Road Multimodal Corridor Profile Study May 2007<br />
Final Report Page 2-14