Audit <strong>of</strong> <strong>Vital</strong> Registration and <strong>Vital</strong> <strong>Statistics</strong> Systems: <strong>Jamaica</strong><br />
Recommendations Implementation Work Plan<br />
Task<br />
20.5.1.1. Gather requirements for the specific system<br />
20.5.1.2. Finalize functional requirements<br />
20.5.2. Tender process<br />
20.5.2.1. Prepare RFP’s & advertise tender notices for hardware & s<strong>of</strong>tware<br />
20.5.2.2. Receive tenders<br />
20.5.2.3. Evaluate tenders<br />
20.5.2.4. Prepare contracts for the vendors<br />
20.5.2.5. Award tenders<br />
20.5.2.6. Get contracts signed<br />
20.5.2.7. Prepare implementation project plan<br />
20.5.3. Install Hardware specific to the system<br />
20.5.3.1. Assemble parts<br />
20.5.3.2. Install, configure operating system<br />
20.5.3.3. Test connectivity with other systems<br />
20.5.4. Data Conversion from current system (PAS: Patient Admissions System) for<br />
export into new system<br />
20.5.4.1. Export data from PAS system to flat files<br />
20.5.4.2. Integrate Unique ID (if possible)<br />
20.5.4.3. Develop scripts to migrate data<br />
20.5.4.4. Scrub and re-format data<br />
20.5.5. Install test system<br />
20.5.5.1. Set up static information<br />
20.5.5.2. System configuration & customization<br />
20.5.5.3. Load patient data from PAS converted files<br />
20.5.5.4. Test application with new data<br />
20.5.6. Design Interfaces<br />
20.5.6.1. Gather requirements<br />
20.5.6.2. Finalize Functional requirements<br />
20.5.6.3. Customize, Test, Implement Interface to other systems<br />
20.5.7. Install production system<br />
20.5.7.1. Set up user security and privileges<br />
20.5.7.2. Set up static information<br />
20.5.7.3. Load patient data<br />
20.5.8. Testing / Quality Assurance<br />
20.5.8.1. Perform unit test<br />
20.5.8.2. Perform Integration test<br />
20.5.8.3. Perform system / load test<br />
20.5.9. Training<br />
20.5.9.1. Identify users / venue<br />
20.5.9.2. Schedule resources (users, venue, equipment)<br />
20.5.9.3. Train Administrator<br />
20.5.9.4. Train Users<br />
20.5.10. Implementation<br />