(c) Blowholes not more than about 10mm in diameter will be permitted but otherwise surface is to<br />

be free from voids honey combing and other large defects .<br />

(d) Variation in colour resulting from the use of an from discolaration due to contamination or grout<br />

leakage .<br />

The finish will be left as struck , making good or small defects will normally be permitted but only<br />

after inspection by the Engineer. All blowholes shall be filled with a matching mortar to an<br />

approved sample unless otherwise instructed by the Engineer. All faces shall be protected from<br />

damage , especially arrisses .<br />

All faces shall be protected from rust marks and other surface disfigurements. Form tie holes shall<br />

be filled with a matching mortar to an approved sample accepted by the Engineer .<br />

2 - Fine finish ( Fair Face)<br />

General Requirements :<br />

a) Produce a smooth even finish with an impervious sheet metal .<br />

b) Make panels as large as is practicable and arrange to approval .<br />

c) Blowhole not more than about 5mm in diameter will be permitted but otherwise surface is to be<br />

free from voids, honey combing and other defects .<br />

d) Variation in colour resulting from the use of an impervious form lining will be permitted , but the<br />

surface is to be free from discoloration due to contamination or grout leakage .<br />

e) Concrete cover spacers shall be used only if approved .<br />

The finish is to be left as struck . Making good will not normally be permitted . All form tie holes<br />

are to be filled with a matching mortar to an approved sample . Wire form ties shall not be used .<br />

Approval of the Engineer for the position of tie holes is to be obtained before use .<br />

Quality Control Testing Etc.<br />

Prior to commencing the work the contractor shall make available on site the following minimum<br />

approved equipment kept in good condition at all times :<br />

- Six Cube moulds .<br />

- Slump cones .<br />

- Thermometer .<br />

- Any other accessories as required by the Engineer .<br />

All samples and testing shall be done in the presence of the Engineer or his authorised representative<br />

either on site or in an approved testing laboratory in the area .<br />

The frequency of testing shall be as noted in the clauses of this section and whenever required by<br />

the Engineer.<br />

The works Test Cubes shall be made as follows for types of concrete (A) , (B) , and (C) :<br />

(a) At least three times weekly per mixing plant .<br />

(b) At least once for three individual parts of the structure .<br />

(c) At least once per 100 cubic meters of Concrete or fraction thereof .<br />

For types (D), and (E) concrete the rate shall be once per each 100 cubic meters or fraction thereof .<br />

At least six cubes shall be made at one time . Two of the six cubes are to be tested at seven (7) days<br />

. The remaining four cubes are to be tested at 28 days , and their average strength must not fall below<br />