5.2<br />
<strong>Locomotive</strong> Duty Cycle<br />
The duty cycle is an element <strong>of</strong> the daily locomotive utilization pr<strong>of</strong>ile. An explanation <strong>of</strong> what constitutes the<br />
<strong>Locomotive</strong> Utilization Pr<strong>of</strong>ile and where the duty cycle fits in the pr<strong>of</strong>ile is given in the Glossary <strong>of</strong> Terms. Duty<br />
cycles are determined by evaluating the time spent at each power notch level for a statistically significant sample <strong>of</strong><br />
locomotives. Shown in Table 8 below are duty cycle values as <strong>of</strong> when updated for the various freight services, that<br />
is, Class I mainline, road switching, yard switching, regional lines and short lines, plus intercity and commuter rail<br />
passenger services. Duty cycle updates <strong>of</strong> regional mainline freight and commuter services were done in 2008 while<br />
the most recent updates <strong>of</strong> other services were undertaken in 2007. Of note is that the percentage <strong>of</strong> time-at-idle<br />
<strong>of</strong> Class I mainline locomotives has reduced. This has been due primarily to the installation <strong>of</strong> automatic anti-idling<br />
devices and a strict manual shutdown policy. The increased use <strong>of</strong> such engine shutdown procedures has led to lower<br />
fuel consumption and emissions generated.<br />
Table 8<br />
Duty Cycle by <strong>Locomotive</strong> Service and Year <strong>of</strong> Update<br />
Per cent <strong>of</strong> Engine Operating Time<br />
2007 - 2008 Updates<br />
2001 Update<br />
1990 Update<br />
Idle N1 N2 N3 N4 N5 N6 N7 N8 DB<br />
2007 Class I Mainline Freight 51.3 4.7 5.7 4.7 3.8 3.2 3.0 1.6 14.0 8.0<br />
2007 Class I Road Switch 77.6 4.3 4.4 2.8 2.2 1.4 1.1 0.6 3.2 2.4<br />
2008 Regional Mainline Freight 67.4 8.3 4.9 4.1 3.5 2.0 2.0 1.6 6.2 0.0<br />
2007 Short Line (Assumed<br />
equivalent to Road Switching) 77.6 4.3 4.4 2.8 2.2 1.4 1.1 0.6 3.2 2.4<br />
2007 Yard Switching 84.9 5.4 4.2 2.2 1.4 0.6 0.3 0.2 0.6 0.2<br />
2007 Intercity Passenger 49.7 16.5 4.9 3.4 2.2 1.3 1.2 0.3 18.3 2.2<br />
2008 Commuter (Note 1) 61.4 2.3 2.2 2.1 1.3 1.2 1.8 24.0 3.7<br />
2001 Freight Class I 58.1 3.9 5.0 4.4 3.7 3.3 3.0 1.5 12.0 5.1<br />
2001 Freight Train 61.6 3.8 4.7 4.1 3.5 3.1 2.8 1.5 10.9 4.0<br />
2001 Passenger 69.5 0.5 4.8 2.1 1.4 1.2 0.8 0.2 19.5 0.0<br />
2001 Switching 83.0 4.1 4.0 3.6 2.0 1.0 0.5 0.3 1.5 0.0<br />
1990 Freight 60.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 12.0 0.0<br />
1990 Branch/Yard 81.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 5.0 0.0<br />
Note 1: 2008 Commuter – Idle and N1 are the same power notch position<br />
16 LEM 2008