• SENG acquired the building permit for the gravel<br />
barrier on the Soča River above HPP Doblar.<br />
April<br />
• On 4 April, DEM started the completely renovated<br />
driver of turbine 2 at HPP Zlatoličje for the first time.<br />
• Thorsten Diercks, Ph.D., Secretary General of the<br />
European Association for Coal and Lignite − Euracoal<br />
came to the Šalek Valley in early April for a twoday<br />
visit. He visited PV and TEŠ, and learned about<br />
the technological achievements and plans of both<br />
companies.<br />
• DEM was ranked second among the TOP 101 Slovene<br />
companies in 2007 based on two indicators:<br />
added value per employee and the operating profit/<br />
operating revenues ratio.<br />
• After replacing the hydro-mechanical and electrical<br />
equipment, SENG began trial operations at SHPP<br />
Jelenk.<br />
May<br />
• The Supervisory Board of <strong>HSE</strong> approved the Annual<br />
Report of the Company and the <strong>HSE</strong> Group for 2007.<br />
• The members of the <strong>HSE</strong> Supervisory Board appointed<br />
Viljem Pozeb, M.Sc., the then Assistant Director,<br />
new director of the company. Together with<br />
Jože Zagožen, Ph.D., he constitutes the <strong>HSE</strong> management.<br />
• DEM celebrated the 90th anniversary of HPP Fala.<br />
• TEŠ held a ceremonial opening of the first 42 MW<br />
gas turbine for producing electricity and introduced<br />
natural gas in addition to coal.<br />
• SENG signed a contract on BPP, PT and WEP documentation<br />
for the reconstruction of HPP Doblar 1,<br />
phase II.<br />
• The company TEŠ gained accreditation from the coal<br />
and desulphurisation testing laboratory.<br />
• PV created the Energy Office, tasked with constant care<br />
for rational and optimal use of energy in the PV Group.<br />
• TEŠ adopted the 2008 Business Plan.<br />
June<br />
• An annex was signed to the Concession Contract on<br />
utilisation of the energy potential of the lower Sava<br />
River, enabling the transfer of the concession right<br />
to HESS.<br />
• TEŠ signed a contract on the supply of main 600 MW<br />
technological equipment for Unit 6.<br />
• In co-operation with partners from the Pomurje region,<br />
DEM founded the Pomurje Development Institute<br />
(PRI), which is, in addition to expert tasks, also<br />
assigned an important role in bringing the project<br />
for constructing an HPP on the Mura River closer to<br />
the interested public.<br />
• After the reconstruction of HPP Ajba1 and successful<br />
initial trial start-up, SENG successfully passed<br />
the technical inspection.<br />
• <strong>HSE</strong> increased the capital of the subsidiary TEŠ to<br />
€ 15,794,000.<br />
• PV hosted the international workshop "Mine Greenhouse<br />
Gases CO 2<br />
and CH 4<br />
– Safety, Prevention, Management<br />
and Utilisation".<br />
• PV organised events on Miner's Day. At the 48th<br />
"Jump over the skin", 51 novices took on the mining<br />
profession and the honorary jumper was Uroš Rotnik,<br />
Ph.D., Managing director of TEŠ. Moreover, the<br />
best colleague and working group were announced.<br />
July<br />
• The subsidiary <strong>HSE</strong> Bratislava was established in<br />
Slovakia on 23 July 2008.<br />
• On 1 July 2008, the joint venture was transferred to<br />
the newly founded company HESS.<br />
• The General Meeting of <strong>HSE</strong> Invest re-appointed the<br />
current members of the Supervisory Board for another<br />
4-year term, as their term of office expired.<br />
August<br />
• PV witnessed a record daily progression entailing an<br />
8.5-metre G2/B excavation in the northern branch of<br />
the Preloge pit.<br />
• HESS became a concessionaire on the lower Sava<br />
River.<br />
• As the sole owner of DEM and TEŠ, <strong>HSE</strong> passed a<br />
resolution of the payment of accumulated profit in<br />
the amount of € 24 million for DEM and € 2.8 million<br />
for TEŠ.<br />
September<br />
• <strong>HSE</strong> drew a long-term loan from the EIB in the<br />
amount of € 74 million, granted for financing the<br />
investments in HPP Blanca and HPP Krško for the<br />
period of 20 years.<br />
• The company Hidro Moćnost Makedonija d.o.o., in<br />
which <strong>HSE</strong> holds a 33% stake, was founded in Skopje<br />