TEŠ's Unit 6, 600 MW<br />

Considering the requirements for increasing electricity<br />

production due to ever greater consumption by end<br />

users, the existing units of TEŠ will be upgraded by<br />

additional production capacity – Unit 6 with projected<br />

power of 600 MW. Parallel to that, older units whose<br />

life span is nearing the end or which are technologically<br />

obsolete will be replaced.<br />

The importance of this project not only for the company<br />

but also for Slovenia is demonstrated by the fact that<br />

the project has been included in the National Development<br />

Project Resolution 2007–2023. Using 4 million<br />

tonnes of coal, TEŠ’s annual electricity output, which<br />

now amounts to 3,600 GWh, would increase to 4,700<br />

GWh if the project is implemented. The fact that the impact<br />

on the environment is reduced thanks to the improved<br />

efficiency of modern plants is also significant.<br />

The construction of Unit 6 is planned to be financed<br />

from several sources. In September 2007, an agreement<br />

was signed with the EIB on a long-term loan of<br />

€ 350 million.<br />

The Official Journal of the EU in March 2008 published<br />

a tender for supply of a flue gas desulphurisation device<br />

and in September 2008 a tender for the supply<br />

and installation of a 400 kV GIS switchyard. Tender<br />

documentation for the supply of a cooling water system<br />

is being prepared – construction and preparatory<br />

work – for the purpose of setting up the cooling tower<br />

and implementing other preparatory work. In June<br />

2008 an agreement was signed on the supply of the<br />

main technological equipment.<br />

The project investor is TEŠ.<br />

The main advantage of new technology is better utilisation<br />

of the energy source. Unit 6 will instead of 4 use<br />

3 million tonnes of lignite to produce the same quantity<br />

of electricity as generated by Units 1–5 in 2007.<br />

CO 2<br />

emissions per unit of energy produced will be reduced<br />

from 1.2 kg/kWh to 0.85 kg/kWh. Owing to even<br />

more efficient flue gas desulphurisation devices, SO 2<br />

emissions will be reduced by two thirds, amounting to<br />

less than 2,000 tonnes per year, whereas NO x<br />

emissions<br />

will equal no more than one fourth of the current<br />

figure, also not exceeding 2,000 tonnes per year.<br />

The consumption of process water will almost halve,<br />

resulting in smaller fluctuation of the water level in<br />

Družmir Lake. Noise levels in the environment will go<br />

down by as much as 70%. Moreover, less ash will be<br />

generated per unit of electricity produced.<br />

As the construction will be complex and extensive, it<br />

will be divided into several phases. The construction<br />

work is planned to start with the demolition of the<br />

cooling towers of Units 1–2 and 3 in 2010. Unit 6 is<br />

projected to start operating on a trial basis in 2014.<br />

Planned construction schedule:<br />

• 2009 – construction of the new telecommunications<br />

centre;<br />

• 2010 – demolition of cooling towers 1–2 and 3;<br />

• 2010 – start of Unit 6 construction;<br />

• 2012 – installation of equipment;<br />

• 2014 – trial operation;<br />

• 2015 – regular operation.<br />

Upgrade of TEŠ's<br />

Units 4 and 5<br />

The installation of two gas turbines at Units 4 and 5 increased<br />

the rated capacity of the units by a total of 84<br />

MW. The investment resulted in higher electricity production,<br />

while consuming the entire planned quantity<br />

of coal, and a lower CO 2<br />

emission factor per kWh.<br />

Work on the project to upgrade Units 4 and 5 through<br />

the installation of gas turbines progressed as planned.<br />

<strong>ANNUAL</strong> <strong>REPORT</strong> <strong>HSE</strong> | BUSINESS <strong>REPORT</strong><br />

61

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!