14.01.2015 Views

October 2009 - South Tahoe Public Utility District

October 2009 - South Tahoe Public Utility District

October 2009 - South Tahoe Public Utility District

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

season when ample water is available for diversion. The Alpine Decree mandates that a water<br />

right can not be diverted from the river at a rate greater than 40% per month; this is known as<br />

the 40:40:20 diversion rate.<br />

The conceptual cost of piping the distance from the West Fork of the Carson River to the<br />

Harvey Channel, approximately 10,500 feet, is $3.0 million.<br />

Alternatively the existing ditch could be enlarged in place with short piped sections for areas<br />

where erosion and steep hillside locations. This would reduce the capital cost but operation and<br />

maintenance costs would continue and seepage in the ditch would persist.<br />

Finally, if the C-Line extension to bypass Harvey Place Reservoir were constructed, the<br />

abandoned portion of the C-Line (see Figure 9.1 at the end of Section 9) could be utilized for<br />

Snowshoe Thompson No. 1 flows. Construction of two short connector pipelines between the<br />

Ditch and the aforementioned section of C-Line would be the only additional infrastructure<br />

required.<br />

11.1.2 Project Considerations<br />

Constructability of the pipeline in its existing alignment is a major hurdle to the completion of this<br />

project. The side hill that the alignment runs along is steep and unstable. Traditional open<br />

trench methods may need to be modified in order to use the existing alignment. There are<br />

several environmental concerns addressed in the Environmental Impact Report that may dictate<br />

the construction schedule.<br />

11.1.3 Phase 1 – Diversion to Highway 89<br />

Phase 1 of the Snowshoe Thompson No. 1 reconstruction is planned to commence at the head<br />

works of the split of Millich Ditch. The existing concrete structure will be modified to incorporate<br />

a debris screen and gate. Phase 1 reach totals 2,900 linear feet that is planned to be replaced<br />

with 36-inch diameter pipe. Periodically along the alignment sediment sumps should be<br />

constructed to aid in pipeline maintenance. Prioritizing construction of Phase 1 is important to<br />

minimize the <strong>District</strong>‟s operational constraints during high runoff events, and convey the<br />

maximum allocated volume of water to Indian Creek Reservoir.<br />

11.1.4 Phase 2 – Highway 89 to Upper Dressler Ditch<br />

Phase 2 improvements are less critical than the upstream Phase 1 reach. The existing capacity<br />

is less hindered throughout this reach; however transmission losses are quite high. Phase 2<br />

improvements includes approximately 8,700 linear feet of ditch conversion to 36-inch diameter<br />

pipe. Alternatively, the abandoned portion of C-Line could be utilized for Snowshoe Thompson<br />

No. 1 flows, considerably reducing the Phase 2 improvements.<br />

11.2 Project No. 15 - Upper Dressler Ditch Conveyance<br />

Improvements<br />

This project addresses the purpose and need statement:<br />

<br />

PN-9. Ability to meet Indian Creek Reservoir water quality requirements is impaired and<br />

the <strong>District</strong> needs to meet TMDL requirements for the Indian Creek Reservoir.<br />

<strong>South</strong> <strong>Tahoe</strong> <strong>Public</strong> <strong>Utility</strong> <strong>District</strong><br />

Recycled Water Facilities Master Plan - <strong>October</strong> <strong>2009</strong> Page 11-82

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!